Forum quick links
No cooling in Proposed Building
CS-2009 EAp2:Minimum energy performanceposted by Johannes Hopf on
Our proposed building has no cooling system installed; it is ventilated naturally. Now Appendix G says to model the proposed building like the baseline bldg system. That means with a VAV.
Tenant lighting exceeds ASHRAE, how to model?
CS-2009 EAp2:Minimum energy performanceposted by Aaron Yorke on
Hello all, In LEED - CS office projects, since the tenant fitout is unknown, LPD is modeled 12 W/m2 according ASHRAE. However, in the country we are working, national standart for LPD is 20 W/m2.
Thin Client
CS-2009 EAp2:Minimum energy performanceposted by Michela Tedeschi on
Hello all, The owners of the building we are certifying want to evaluate the effects of the thin client (form 150 W/computer to 50W/computer) on EAp2/EAc1.
Error in eQUEST in the Perform Compliance Analysis
CS-2009 EAp2:Minimum energy performanceposted by Toni Herena Montull on
Dear all, I am stuck with an error from eQUEST.
Calculating "Projection Factor" for curtainwall shading devices
CS-2009 EAp2:Minimum energy performanceposted by Amit Ahiel on
I'm working on a project where part of the curtain wall has a few random horizontal elements that project from the vision panels from floor to ceiling. These elements provide shading and therefor
ASHRAE Table 6.8.1 Centrifugal Chillers
CS-2009 EAp2:Minimum energy performanceposted by Redy Truccolo on
Hi, in the table 6.8.1J of ASHRAE 90.1 there is a "condenser Flow rate" parameter, expressed in gpm/ton. My question is: to calculate this parameter do I have to use the nominal refrigeration powe
Modeling Number of Occupants - Which Standard?
CS-2009 EAp2:Minimum energy performanceposted by Thomas Newbold on
I am new to LEED modeling and I'm trying to figure out which occupancy information is correct. The building contains retail space.
DHW Equipment Performance; DES Heating
CS-2009 EAp2:Minimum energy performanceposted by Samuel Sura on
Dear all, please help me with these questions: 1) I'm not sure how to specify a water heating equipment performance.
LEED CS if no provision of Tenant's AC system by base building
CS-2009 EAp2:Minimum energy performanceposted by Andrew Xiao Junzhao on
Dear LEEDuser community, I have a project which is about 60 storey commercial office building.
% of Glazing & Floor Area Base Case vs Project
CS-2009 EAp2:Minimum energy performanceposted by Dana Guzman on
Hi, I am new to LEED and looking at the energy model submitted by our consultant for the compliance on EAp2. I have a basic question.