The fan power consumption calculation of PSZ-HP system
Retail-CI-v4 EAp2:Minimum energy performanceposted by JAMES CHEN on
questions:
1. Our current total area of the model: Total Building Area: 191.5 m2, Net Conditioned Building Area: 141.90, Unconditioned Building Area: 49.60m2, 2 Floor
Fenestration - Baseline vs. Proposed
NC-v4 EAp2:Minimum energy performanceposted by Fábio Batista on
Hi all,
I have 3 questions to ask:
1.
Documentation for Material Reuse?
NC-v4 MRc3:Building product disclosure and optimization - sourcing of raw materialsposted by Megan White on
What is required for documentation of material reuse? In the Ref Guide (p.535), it says projects should track original location of the material before remove.
How to conduct Cost-Benefit Analysis
EBOM-v4 EAc7:Renewable energy and carbon offsetsposted by Hamzeh Saqer on
I just need to know how to conduct the cost-benefit analysis (step 6) for a PV array on-site owned by a third party.
Modeling DOA in Baseline for residential project
NC-v4 EAp2:Minimum energy performanceposted by Saif Abdulameer on
I am working on a small hotel that is served by VRF units and DOA unit which dehumidify and reheat the OA for the guest rooms, when creating the Baseline system (system 2 for this project) should i
LEED ID+C CI commercial Interiors v4 water calc credit
CI-v4 WEc1:Indoor water use reductionposted by Robert Fernandez on
A little confused on this aspect of the credit....I was told buy a colleague that this credit can only apply to newly installed fixtures? and not base building restrooms that were not modified?
Option 2 site area
CS-v4 SSc2:Site development - protect or restore habitatposted by Gail Napell on
Hi all
just confirming this is literally based on site area -i.e. our site is very small, so the cost is proportional. Thank you!
Distance between bicycle racks and functional/main entry
Warehouses-NC-v4 LTc6:Bicycle facilitiesposted by Agnieszka Rylska on
This credit requires provision of bicycle racks within 30m of any main/functional entry.
MR - Construction and Demolition waste Management: Group Approach
NC-v4 MRc5:Construction and demolition waste managementposted by MAUDE PINTAL on
We have a certified LEED-NCv4 project located on a site pursuing a LEED-ND certification.
Credit for minimizing hardscape
NC-v4 SSc5:Heat island reductionposted by Bret Mantyk on
Is there anyway to claim credit for having a lot of vegetated landscapes on a project - which meets the intent of reducing heat islands?