VOC content in wet-applied products vs CIAQMP requirements
NC-v4 EQc3:Construction indoor air quality management planposted by Agnieszka Rylska on
Hello!
I have a question concerning SMACNA requirements. There is the sentence in LEED reference guide:
Transportation rate threshold between 45% and 50%
EBOM-v4 LTc1:Alternative transportationposted by Laura Danzig on
Hi all,
Outdoor Air for Corridors and Stairs
CS-v4 EQp1:Minimum indoor air quality performanceposted by Ciaran McCabe on
ASHRAE 62.1 requires outdoor air to be provided to corridors - stairs seems to be a grey area ?. If you are using Option 2.
100% Previously Developed Site with National trees
NC-v4 SSc2:Site development - protect or restore habitatposted by Ahmed Labeeb on
We are working on a project located in Dubai, UAE. The total site area was previously developed by an old owner.
Runoff calculations & rainwater harvesting
EBOM-v4 SSc2:Rainwater managementposted by Gail Vittori on
If I can calculate the volume of runoff using the site impervious area in square feet and the 95th percentile rainfall over 24 hours in inches, do I also need to use one of the tools identifie
Shop-applied primer/touch-up paint for field
NC-v4 EQc2:Low-emitting materialsposted by Shaunna Shaw on
I work for a structural steel contractor working on our first LEED v4 project and we are having difficulty getting our standard shop primer approved by the GC. The paint does not meet th
How to calculate the Tank size
NC-v4 SSc4:Rainwater managementposted by Patrick Y P Lui on
I am working a hotel project with 6090 sq.m greenery + 14210 sq.m pavement and willing to get 3 points by Percentile of rainfall events (Option 1) - Path 2 98th Percentile.
Renewable fuels and "green" natural gas?
CS-v4 EAc7:Green power and carbon offsetsposted by Adolfo Silva on
Is it possible to account for externally-produced renewable fuels in the "total energy use" calculation?
Office, conference room to Hallway, stairs STCc Interpretation
CI-v4 EQc9:Acoustic performanceposted by Jeffrey Fullerton on
In this credit, there is a requirement for an STCc 50 rating for "Office, conference room" to "Hallway, stairs".