Example confusion in Ref Guide

EBOM-v4 MRc3:Purchasing - facility maintenance and renovation
posted by  Lorne Mlotek  on 

On page 367 example 1 The carpet meets the extended producer responsibility criteria which should count 50% of its value - but the entire 100% is counted. Which is correct?

1
Thu Jul 17, 2014, 12:26 am

Final Report

NC-v4 EAc1:Enhanced commissioning
posted by  Colin Grist  on 

Hello all, I am wondering if there are guidelines for what should be included in the eCx final report. Is there a template or list of items that should be included? Thank you, Colin

1
Tue Dec 13, 2016, 6:32 pm

Solid Surfacing Materials in LEED v4

NC-v4 EQc2:Low-emitting materials
posted by  Amit Ahiel  on 

Are solid surfacing materials considered in this credit under furniture?

1
Sun Jan 11, 2015, 4:27 pm

Bicycle Facilities - Bicycle Network

NC-v4 LTc6:Bicycle facilities
posted by  Vasileios Kalfountzos  on 

Hello everyone, I am currently working on a project located on a relatively industrialised area. That being said, due to the nature of the area there aren't any bicycle networks around the area.

1
Mon Mar 6, 2017, 7:51 pm

Energy performance vs. Energy Cost

Mid-Rise-v4 EAc1:Annual energy use
posted by  Eesmyal Santos-Brault  on 

Hi - It seems that this version of the rating system is targeting energy performance improvement over energy cost budget. Is that right?

1
Tue Jan 17, 2017, 8:58 pm

Brownfield site

Hospitality-NC-v4 LTc3:High priority site
posted by  Karen Heet  on 

Howdy! Can this credit be achieved if the project is on a former brownfield site - meaning that it was identified and already remediated by the previous owner? Many thanks!

1
Mon Aug 24, 2015, 7:54 pm

Confidential space

CI-v4 MPR2:Must use reasonable LEED boundaries
posted by  Ameet AA  on 

Hi, The project is a 3-storey high building, single tenant. The tenant already occupies the building, and going to renovate about half of the floor area.

1
Mon Apr 17, 2017, 9:50 pm

Who can be the CxA?

CI-v4 EAc1:Enhanced commissioning
posted by  emily reese moody  on 

Under v3, if a project wanted to pursue the enhanced Cx credit, a third-party CxA was required, and that entity completed the activities for both the prerequisite and the enhanced credit. Have the

1
Sat Mar 19, 2016, 12:06 am

VOC emissions certificate

NC-v4 EQc2:Low-emitting materials
posted by  Charline SEYTIER  on 

We received a LEED approved certificate concerning VOC emissions for Polyethylen Foam products.

1
Tue Jul 4, 2017, 4:19 pm

Distance from water bodies and wet lands

NC-v4 LTc2:Sensitive land protection
posted by  Bazeeth Ahamed K M  on 

In V3, the development boundary from water bodies and wetlands should be 50' and 100' respectively. Why in V4 it is reversed ie 100' for water bodies and 50' for wetland? Any justification?

1
Fri Nov 8, 2013, 9:31 pm