Forum quick links
Material reuse calculation
NC-v4 MRc3:Building product disclosure and optimization - sourcing of raw materialsposted by Jen Roberts on
The second example on pg 536 of the reference guide is a bit confusing.
Turf-grass area
NC-v4 SSc2:Site development - protect or restore habitatposted by Jody Lee Potvin-Jones on
Hello all. Our site consists of an existed building that is going to be demolished, some paved areas and approximately 30% of green areas with turf-grass and few trees.
Operable windows -ground floor or upperfloor?
NC-v4 EQp2:Environmental tobacco smoke controlposted by Florian Schmidtchen on
Dear Sir or Madam, Smoking must be prohibited within 25 feet of building entries, outdoor air intakes, and operable windows.
diverse uses
NC-v4 LTc4:Surrounding density and diverse usesposted by sepideh khodadadi on
our project is a big shopping center with almost all the diverse uses (such as restaurant,bank,etc.) can that help us get the credit without calculating the surrounding diverse uses?
Existing building - applicable requirements
CI-v4 EAp2:Minimum energy performanceposted by Ricardo Sá on
I'm working in a project of an existing building refurbishment that will pursue LEED certification CI.
enhanced refrigeration management credit
NC-v4 EAc6:Enhanced refrigerant managementposted by david gordon on
can someone explain how/why a credit is achieved under the LEEDv4 , enhanced refrigerant management.
Walkway versus public street
NC-v4 SSc6:Light pollution reductionposted by Jens Apel on
This may be an academic question but I am unsure on the wording. The modification of the lighting boundary depends on adjacency to a walkway or a public street.
Recycling infrastructure - inconsistency in reference guide
ND-Plan-v4 GIBc16:Solid waste managementposted by Nate Tsang on
The requirements and the step-by-step instructions are inconsistent.
ESv3 checklists
Mid-Rise-v4 EAp1:Minimum energy performanceposted by Sue Bryant on
The EAp1 v4 requirement is to meet ESv3 by completing the thermal enclosure system rater checklist, the HVAC system quality install rater and contractor checklist and the water management system bu
Lighting Sales areas
Retail-CI-v4 EQc6:Interior lightingposted by Guillaume PAJOT on
Hi, I am working on a store where the sale area is composed of ligthing for furniture and ambiant lighting in ceiling.