Post a question or comment
Credit Filters
Stormwater design - quantity control
Filter by location
Forum
Topic
Replies
Recent

Drainage Pipe Capacity

NC-2009 SSc6.1:Stormwater design - quantity control
posted by  Jatuwat Varodompun  on 

Can we count the capacity of underground drainage pipes as the retention capacity? The pipe capacity will then add to the stormwater retention capacity.

1
Mon Feb 18, 2013, 12:18 pm

Peak discharge/flow rate

NC-2009 SSc6.1:Stormwater design - quantity control
posted by  hana manai  on 

Which formula do you use to calculate peak flow rate (1 and 2-year, 24hours). I am using NRCS (SCS) TR-55 Graphical Discharge Method. Is that recommanded?

1
Mon Dec 28, 2015, 10:50 pm

LEED Runoff Coefficients for BMPs

NC-2009 SSc6.1:Stormwater design - quantity control
posted by  Timothy Brown  on 

I am finding it difficult to locate standard CN values for BMPs. There are not many studies out there and the ones I have found have calculated large ranges for permeable pavers, green roofs etc.

2
Regional Stormwater Leader
Arcadis North America
LEEDuser Expert
144 thumbs up
Mon Jun 19, 2017, 1:36 pm

No 2-year, 24 hour design storm data available

NC-2009 SSc6.1:Stormwater design - quantity control
posted by  Mario S.  on 

The 2 year, 24-hour design storm precipitation data is unavailable for the country. However, Historic rainfall data exists.

2
Regional Stormwater Leader
Arcadis North America
LEEDuser Expert
144 thumbs up
Fri May 12, 2017, 6:39 am

swimming pool

NC-2009 SSc6.1:Stormwater design - quantity control
posted by  Melissa Merryweather  on 

Hi --can a swimming pool be considered a retention pond? And are swimming pools considered to be 100% pervious? Or is it a matter of whether the water is treated before re-use or release?

2
Regional Stormwater Leader
Arcadis North America
LEEDuser Expert
144 thumbs up
Fri Dec 30, 2016, 3:49 am

Terms and concepts used in the form

NC-2009 SSc6.1:Stormwater design - quantity control
posted by  Gabriela Mesquita  on 

Good morning, We are working in a Project in Asunción, Paraguay.

2
Regional Stormwater Leader
Arcadis North America
LEEDuser Expert
144 thumbs up
Wed Aug 31, 2016, 4:11 pm

Time to utilize water volume - International project

NC-2009 SSc6.1:Stormwater design - quantity control
posted by  Maria Isabel Conde  on 

Hello, In our project outside the US and in the rainy tropics our site pre-development is >50% impervious (only 10% site is natural green) therefore we need to go for 25% reduction in both volu

4
Wed Mar 23, 2016, 6:09 pm

Underground Storage Chambers

NC-2009 SSc6.1:Stormwater design - quantity control
posted by  Marco Valerio Ceccotti  on 

To reduce runoff peak and quantity our project team used an embedded underground chambers system.

3
Mon Feb 8, 2016, 2:59 pm
5
Sun Dec 20, 2015, 12:55 pm

IDF curves

NC-2009 SSc6.1:Stormwater design - quantity control
posted by  MKK LEED  on 

Hi, I have a NC project in Colombia and the Environmental Authority just have IDF curves since 3 years. I don't have information since 1 and 2 years.

4
Regional Stormwater Leader
Arcadis North America
LEEDuser Expert
144 thumbs up
Wed Jul 22, 2015, 6:55 pm