NC-2009 EAp2:Minimum energy performanceposted by Bala Srini on
Our semi industrial building's production area does not have cooling system, Proposed model simulated based on ASHRAE 90.1-2007, Table G3.1, 10. HVAC No.
Waste Oil Fuel
NC-2009 EAp2:Minimum energy performanceposted by Michael Daly on
I am working on a project that has two parts to the building. There is an office component and a shop component. The office is going to be heated and cooled with a VRF system.
Complex credit compliance?
NC-2009 EAp2:Minimum energy performanceposted by Kath Williams on
Project location: National Park Project Scope: Relocation of historic building Designation: Retains SHPO designation MR Credit 2: CIRs state relocation results in contributing to Material Reuse cr
water cooled chillers
NC-2009 EAp2:Minimum energy performanceposted by sherif el adly on
Hi Marcus, I am working on a project in KSA of about 404330ft2.
LEED 2009 EAp2 Update
NC-2009 EAp2:Minimum energy performanceposted by Ward Miller on
Perhaps the wrong thread, but as the update is mentioned here, does anyone happen to know whether a performance requirement update for EAp2 is also planned for LEED EBOM 2009?
Parking Garages Abutting Conditioned Space
NC-2009 EAp2:Minimum energy performanceposted by Jon Clifford on
While we are on the topic of parking garages, I have had projects where a parking garage abutted a conditioned building.
Trace 700 "LEED Energy Performance Summary Report"
NC-2009 EAp2:Minimum energy performanceposted by Erin Adkins on
For those of you that use Trace 700 and are familiar with the fairly new feature, the "LEED Energy Performance Summary Report", that Provides all the information for each section of the EAp2 templa
CCHP System modeling
NC-2009 EAp2:Minimum energy performanceposted by Jie Shen on
My project is provided by CCHP system which owned by third party, the CCHP has two gas generators, one heat recovered gas absorption chiller, two normal chillers and two boilers.
Wood Chip Boiler base case?
NC-2009 EAp2:Minimum energy performanceposted by Allison Zuchman on
This is a question from a non-energy modeler looking for some guidance on base case vs. design case for a LEED energy model that a consultant is working on. The project is a school.
Magnetic bearing Chillers
NC-2009 EAp2:Minimum energy performanceposted by Rudolph Carneiro on
Hello all. Does anyone have experience with justifying that the lower full load efficiency of magnetic bearing chillers is ok due to their exceptionally high IPLV? ASHRAE 90.1-2007 and ARI 550/59