Exterior lighting part of 25% process load requirement?

NC-2009 EAp2:Minimum energy performance
posted by  Catalina Caballero  on 

Can exterior lighting be part of the 25% process load requirement by Ashrae 90.1-2007 when it comes to energy modeling?

1
Tue Apr 8, 2014, 7:09 pm

No longer required to complete Design prereqs before review?

NC-2009 EAp2:Minimum energy performance
posted by  Susan Di Giulio  on 

From what I have read about the new website, it is no longer required to complete all design prerequisites before submitting for Design Review (split review assumed).

1
Thu Jan 15, 2015, 3:44 am
1
Tue Sep 21, 2010, 12:37 pm

DES Option 1 - Baseline System Heating Type Clarification

NC-2009 EAp2:Minimum energy performance
posted by  Mike Ramos  on 

We're using Option 1 of the "Treatment of District or Campus Thermal Energy in LEED v2 and LEED 2009 - Design and Construction" document to comply with EAp2 / EAc1.

1
Mon Nov 2, 2015, 5:59 pm

Equipment as per table 6.8.1.A 90.1-2007

NC-2009 EAp2:Minimum energy performance
posted by  Vassil Vassilev  on 

Greetings, In the project we are modeling, there are air conditioners which are supposed to operate in cooling mode at OA temperature close to the design heating OA. In this table and also in othe

1
Tue Aug 15, 2017, 4:50 pm

Cogen Gas Rates

NC-2009 EAp2:Minimum energy performance
posted by  Wes Lawson  on 

Hello all, We are attempting to model a cogen system (using gas to create electricity and using waste heat for domestic water heating). My questions are as follows: 1.

1
Wed May 14, 2014, 2:04 pm

District virtual rate:

NC-2009 EAp2:Minimum energy performance
posted by  Haojie Wang  on 

We have project using district steam. We use DES v2 to calculate the virtual rate based on state averaged electricity (0.084$/kWh) and gas (0.00757$/MBTU).

1
Thu Mar 5, 2015, 5:14 pm

Air leakage through revolving door

NC-2009 EAp2:Minimum energy performance
posted by  Claes Engström  on 

Hi ! According to building envelope compliance documentation Part I, revolvning doors should have air leakage less than 1,0 cfm/ft2. A manufacturer of revolving doors informed me that all revolvin

0

Solar service hot water system

NC-2009 EAp2:Minimum energy performance
posted by  Rosana Correa  on 

Hi, The service water system in this building is heated by solar thermal collectors only, with no secondary heating system.

1
Thu Sep 19, 2013, 9:19 pm

Roof insulation & suspended ceiling

NC-2009 EAp2:Minimum energy performance
posted by  Charline SEYTIER  on 

Hi everyone, We are working on a major renovation project where the owner wants to install roof insulation above the suspended ceiling.

1
Tue Jun 17, 2014, 1:38 pm