Forum quick links
Baseline Energy Rates for CHP
NC-2009 EAp2:Minimum energy performanceposted by Gopinath Vasu on
I am working on a project where natural gas generator is used power generation and the waste heat is recovered to run the VAM chiller.
MODEL PROTOCOL
NC-2009 EAp2:Minimum energy performanceposted by RICARDO GUEMEZ on
Hello, My name is Ricardo from Mexico City.
Core Performance Guide
NC-2009 EAp2:Minimum energy performanceposted by Tricia Loe on
I have a project that is considering using the Core Performance Guide option for compliance with this credit.
Plant Design for Proposed bldg
NC-2009 EAp2:Minimum energy performanceposted by Julian Park on
If a new building will be served by an existing chiller plant that already serves an existing building, does the Plant design for the Proposed Alternative need to model the full chiller size, even
ASHRAE 90.1 vs T-24 in california
NC-2009 EAp2:Minimum energy performanceposted by Lance Collins on
Question: I am working on a new LEED-NC project in california that is using a modular/prefab construction type with mechanical systems that do not require permits via the T-24 code.
Chilled Water Pumps, Primary/Secondary
NC-2009 EAp2:Minimum energy performanceposted by Aaron Dahlstrom on
ASHRAE 90.1-2007 Sec G3.1.3.10 requests that users specify pump power of 22 W/gpm, with a primary / secondary pumping system and variable flow on the secondary side.
Conditioned Space
NC-2009 EAp2:Minimum energy performanceposted by Jean Marais on
Consider a space, storage, with no heating, modelled with heating setpoint -50 degC, receives air from a central air handling unit VAV system, where the delivered air is pre-conditioned from Outdoo
Parallel PIU fan energy
NC-2009 EAp2:Minimum energy performanceposted by Magda Aghababyan on
My baseline is under system 6 in which the parallel PIU fans has to be introduced for each zones.