Owner Agent required information

NC-2009 EAc2:On-site renewable energy
posted by  Francisco Villela  on 

Marcus, I am looking at the on-line form for EAc2 On-Site Renewable Energy. (LEED 2009 for New Construction) The asterisk occurs after each of two Required Signatory boxes.

1
Tue Nov 29, 2011, 4:56 pm

PV's special rate

NC-2009 EAc2:On-site renewable energy
posted by  Michela Tedeschi  on 

Hello all, As I understand, all the energy produced by photovoltaic panels which is not used for the building (then fed into the grid) can not be counted for the purposes of credit EAC2.

1
Wed May 22, 2013, 12:59 pm

Probability distribution of annual PV production.

NC-2009 EAc2:On-site renewable energy
posted by  Indochine Engineering VN  on 

Hi, a solar PV consultant gave me an output of their simulation, in which show probability distribution diagram of Solar PV production.

1
Tue Nov 17, 2015, 2:23 pm
1
Mon Jan 24, 2011, 4:13 pm

Landfill Generated Methane Gas

NC-2009 EAc2:On-site renewable energy
posted by  Kendal Neitzke  on 

Our building project is a methane pumping facility located at landfill that is the source of the methane.

1
Thu May 3, 2012, 3:55 pm

PV as a source of energy for ground heat exchange

NC-2009 EAc2:On-site renewable energy
posted by  Samuel Sura  on 

A project I'm working on is considering a combination of PV and ground source heat pump. The PV will generate approx.

1
Mon Dec 2, 2013, 3:46 pm

Annual Energy Cost

NC-2009 EAc2:On-site renewable energy
posted by  Sarah Thompson  on 

I am trying to figure out which cost to put in here. Another post said it was savings, although I can't find anything under the credit intent or resources for this specific item.

1
Wed Feb 18, 2015, 10:30 pm

Biomass Boiler

NC-2009 EAc2:On-site renewable energy
posted by  SAMY Chamy  on 

Dear all our project is located in a rural area. then agriculture waste (Biomass) is available in anywhere near our site.

1
Mon Mar 21, 2016, 10:30 pm

Doubts in Green power & REC

NC-2009 EAc2:On-site renewable energy
posted by  SAMY Chamy  on 

Dear Concern:- Our project have windmill, additionally wind mill capacity is 10 times greater than project connoted load The project use government electricity with net metering every month the

1
Fri May 26, 2017, 3:24 pm

Allocating Green-e Certified power to EAc2 and EA6

NC-2009 EAc2:On-site renewable energy
posted by  Adam Prince  on 

We have a LEED NC project in Massachusetts (Office space with 2 residential units above). On the roof will be a PV system producing just over 50% of the buildings total energy consumption.

1
Mon Jan 13, 2014, 11:36 pm