Buried crushed concrete

NC-2009 MRc3:Materials reuse
posted by  Maria Isabel Conde  on 

We are demolishing an existing building. The team is considering burying the concrete, without this being used as fill for the new building. Could this account for the MRC2? Thanks,

1
Thu Jun 19, 2014, 9:02 pm

Demolished Building - Material Reuse

NC-2009 MRc3:Materials reuse
posted by  Lauren Bellamy  on 

Our client has demolished the existing structures on our site and salvaged all the cladding and flooring materials (i.e.

1
Tue Sep 22, 2015, 8:48 pm

Trees on site to be used for furniture, blocking and/or veneer.

NC-2009 MRc3:Materials reuse
posted by  Seonhee Kim  on 

If some of trees on site need to be cleared and we decide to use it for furniture, blocking and/or veneer, does this count as MRc3?

1
Wed Mar 20, 2013, 11:15 pm

Material Reuse

NC-2009 MRc3:Materials reuse
posted by  Scott Gharda  on 

I am working on a project where we will be renovating an existing 2 story warehouse to turn it into office space.

1
Mon Jan 30, 2017, 10:49 pm

Cost to be Excluded in the total proj material costs for MR CR3

NC-2009 MRc3:Materials reuse
posted by  Benjie Herrera  on 

I just want to inquire if we will include HVAC equipment, PV arrays, Solar hotwater collectors, generator, fire alarm control panels, etc.

1
Wed Sep 21, 2011, 4:29 pm

Salvaged granite block

NC-2009 MRc3:Materials reuse
posted by  Sara Sweeney  on 

Hi I am working on a project where 83.75 tons of granite slabs were removed from a site during site clean-up for the new bilding being built.

1
Mon Jun 11, 2012, 4:12 pm

Salvaged Materials Code Conflict

NC-2009 MRc3:Materials reuse
posted by  Annalise Reichert  on 

I am working on a 17-story multi-family new construction project in California that will not involve any demo of existing structures at the site.

1
Mon Jan 30, 2017, 10:41 pm

Material reuse based on cost or volume

NC-2009 MRc3:Materials reuse
posted by  Mahbuba Khan AIA, LEED AP BD+C  on 

I am working on an international LEED NC 2009 project.

1
Fri Jul 12, 2013, 7:30 pm

Documenting costs and cut sheets

NC-2009 MRc3:Materials reuse
posted by  John Covello  on 

Hello, Our project will be purchasing old teak wood (in good shape) from housing that is to be demolished. The invoices may be simple hand written pages noting the pricing and date.

1
Fri Jul 11, 2014, 2:18 pm

Is soil a material considered on this credit?

NC-2009 MRc3:Materials reuse
posted by  Albert Sagrera  on 

Would you consider the reuse of soil on this credit? The situacion is that the soil extracted for the building construction is not send to dump but it's reused on the modeling of landscape.

1
Wed Jun 6, 2012, 1:08 pm