NC-2009 MRc4:Recycled contentposted by Mariah Grife on
The new LEED language has clarified that 32.10.00 Paving should be included in the construction costs. However, the only paving that will occur on my project's contract will be in-street paving p
Fly ash - Pre or Post?
NC-2009 MRc4:Recycled contentposted by PAWAN DAHIWAL on
Fly ash generated from a thermal plant, used to manufacture bricks.
LEED management for multi-prime contractor project
NC-2009 MRc4:Recycled contentposted by Chris Gutsche on
We have a LEED 2009 institutional project with 12 prime contractors. There is a construction management entity with oversight of the 12 primes.
Seats in a Sports Arena
NC-2009 MRc4:Recycled contentposted by Carolina Vergnano on
Hello there, We all know that furniture does not need to be included in the Materials & Resources credits, right? However, in a Sports Arena where seats are a permanent element of the bleache
Material Costs for Assembled Curtain Wall Systems
NC-2009 MRc4:Recycled contentposted by Chris Stronks on
Our company is a supplier of curtain wall systems to the glazing subcontractor.
Form v03 vs v04
NC-2009 MRc4:Recycled contentposted by Angie Allen on
I am completing the documentation for MRc 4, 5 & 7. Currently, we are working from version 3.0 of the form on LEED Online.
recovered fiber
NC-2009 MRc4:Recycled contentposted by Teresa Bell on
When the recycled content of a wood core material is listed as % pre-consumer, % post-consumer and % recovered fiber, is the recovered fiber to be included in the pre-consumer percentage? The defi
Landscaping - MRc4
NC-2009 MRc4:Recycled contentposted by frederick muscatello on
Can landscape and irrigation materials be included?
Requirements for recycle concrete
NC-2009 MRc4:Recycled contentposted by Dw Barnes on
Is there a certain requirement/specification to use concrete that has been crushed from other sites as a material for another site?