Construction IAQ management plan - before occupancy
Filter by location
Forum
Topic
Replies
Recent

four IEQc3.2 questions....

NC-2009 IEQc3.2:Construction IAQ management plan - before occupancy
posted by  Carrie Laurendine  on 

1) ive looked at space matrix (this is a library project)... from what i gather EVERY space has to count.. even spaces not regularly occupied (mech closet, janitor closet, etc).

1
Sat Nov 16, 2013, 2:07 am

Flush-Out Requirement for a Naturally Ventilated Building

NC-2009 IEQc3.2:Construction IAQ management plan - before occupancy
posted by  Eric Carbonnier  on 

The project is an 8 story residence hall on a university campus. The building is not equipped with a central ventilation system and dorm rooms rely on natural ventilation.

1
Thu Mar 19, 2015, 10:43 pm

majority residential

NC-2009 IEQc3.2:Construction IAQ management plan - before occupancy
posted by  Courtney Royal  on 

Our project is a multifamily building with several common spaces on the cellar, main level, and top level of the building. However, majority of the building is apartment units.

0

Credit 3.2, Option 1, Path 2

NC-2009 IEQc3.2:Construction IAQ management plan - before occupancy
posted by  Douglas Blakeslee  on 

We are the GC for a new small (4,000 SF) Leed Certified fast food restaurant with 3,800 CFM of outside air when occupied. We plan to do our initial 3,500 CF/SF flushout over a weekend.

1
Wed Mar 23, 2011, 2:02 pm

Flush out in tropical climate region (Climate Zone 1)

NC-2009 IEQc3.2:Construction IAQ management plan - before occupancy
posted by  Adi Negara, LEED AP BD+C  on 

Hello, Our project is in Indonesia (Climate Zone 1), which happened have high humidity (70-85%) all year long. Our building design only incorporate natural ventilation and AC (VRF system).

0

Concerning Carpet

NC-2009 IEQc3.2:Construction IAQ management plan - before occupancy
posted by  Omar Elrawy  on 

Dear all, We have a project where we intend to pursue Option 1 Path 1, We will install furniture after completing the flush-out, but the architect is concerned about the carpet install

1
Thu Jul 3, 2014, 8:08 am

Option 2 for a Partially Enclosed Building (LEED NCv2.2)

NC-2009 IEQc3.2:Construction IAQ management plan - before occupancy
posted by  SIG - Sustainability Main Account  on 

We performed IAQ testing to meet IEQc3.2 on a subway station. The IAQ levels passed easily, and our approach was recognized by the LEED reviewer as an appropriate approach.

1
Wed May 13, 2015, 7:20 pm

IAQ Testing path option 2

NC-2009 IEQc3.2:Construction IAQ management plan - before occupancy
posted by  Nanechka Pagan  on 

Hi During construction preliminary review our team received a technical advice that states the following: " it does not appear was performed for each area of the building served by a ventilation s

1
Mon Jul 11, 2016, 9:35 pm

IAQ Testing using screening tool.

NC-2009 IEQc3.2:Construction IAQ management plan - before occupancy
posted by  Marcia Weekes  on 

Has anyone had experience with meeting the IAQ testing requirements using the Directsense IAQ Plus Screening tool from Graywolf Sensing Solutions.

1
Wed Apr 13, 2016, 8:09 am

Flushout of Nonoccupied Spaces

NC-2009 IEQc3.2:Construction IAQ management plan - before occupancy
posted by  Sally Marr  on 

The 26,000 square foot building that I am working on has several spaces that are not served with supply air by the building's ventilation system, including toilet rooms and mechanical and electrica

1
Fri Mar 15, 2013, 4:06 pm