Forum quick links
Airflow metering
EBOM-2009 EAc3.2:Performance measurement - system-level meteringposted by Tapio Peltonen on
Our project building has central air-handlers, which provide heating and cooling for the tenant spaces i.e. heating and cooling by air only.
Minimum Performance Measuring Time
EBOM-2009 EAc3.2:Performance measurement - system-level meteringposted by Marina Andrade on
Greetings, We have a doubt about the credit EA C3.2 from LEED EB O&M. What is the minimum time to measure performance of the major’s building systems by the breakdown of energy?
Performance period duration
EBOM-2009 EAc3.2:Performance measurement - system-level meteringposted by Charalampos Giannikopoulos on
The LEED Online form requests that “monthly and annual summaries of the metered energy usage for each of the subsystems”.
Instantaneous and/or totalized
EBOM-2009 EAc3.2:Performance measurement - system-level meteringposted by James Gray on
For natural gas metering applications, is continuous logging of instantaneous flows a requirement? Most meters just put out totalized pulses, so I'm assuming that's fine... Any thoughts?
Commercial Building with Tenant spaces fully submetered
EBOM-2009 EAc3.2:Performance measurement - system-level meteringposted by Energy Spectrum on
I am wondering if a commercial building, where over 90% of the building is submetered tenant space would qualify for this credit.
Subsystem or End Use Type
EBOM-2009 EAc3.2:Performance measurement - system-level meteringposted by Ran Zhang on
On page 200 of the LEED-EB reference guide, Table 1- Sample Summary of Energy and Metering Capacity lists major energy-consumption subsystems and end-uses.
Gas metering
EBOM-2009 EAc3.2:Performance measurement - system-level meteringposted by Oana Stamatin on
In our office building, the annual Gas Consumption accounts for more than 40% of the total annual energy consumption. The gas is used for Heating and for Cooking (for a Restaurant).
Mixed use meter
EBOM-2009 EAc3.2:Performance measurement - system-level meteringposted by Alicia Villanueva on
We have a meter that measures: chiller + pump + lighting system. Since we are not discriminating by "end use": would this meter qualify towards this credit? Thanks GH
Period & time of Breakdown
EBOM-2009 EAc3.2:Performance measurement - system-level meteringposted by Alexa Stone on
Hi all, I'm confused about when OR over what period of time does the breakdown need to capture. I understand that it needs to roll up to the EAc1 declared annual energy use (mbtu).
EAp2/c1 Metering Requirements Also Earn EAc3.2?
EBOM-2009 EAc3.2:Performance measurement - system-level meteringposted by American University on
If we had to meter things like hot water usage and chillers on a building level to comply with EAp2/c1 to do building-level metering of all incoming energy inputs, would we automatically be able to