Forum quick links
Do I need to document out of scope HVAC equipment?
CI-2009 EAp2:Minimum energy performanceposted by Silvia Ruiz on
Hi, Given that only the portions of the building as covered by the tenant’s scope of work need to comply with ANSI/ASHRAE/IESNA Standard 90.1–2007, do we need to document those that are out of the
ASHRAE 90.1-2007 - 6.4.3.1.1 COMPLIANCE CRITERIA
CI-2009 EAp2:Minimum energy performanceposted by RICARDO HERNANDEZ on
Does anyone know how stringent is the criteria to achieve compliance with the 6.4.3.1.1 Zone Thermostatic Controls for a Commercial Interiors?
new version od LEEDonline form
CI-2009 EAp2:Minimum energy performanceposted by Agnieszka Rylska on
I was checking sample LEEDonline forms for this prerequisite which can be found on USGBC website and I nonticed that there is a new version of EAp2 form - v6.
Envelope requirements of ASHRAE 91.1-2007
CI-2009 EAp2:Minimum energy performanceposted by Cristina Valenzuela on
My client is doing an interior renovation of a small office at the ground floor in an existing mixed-use building.
Detailed Plant Simulation
CI-2009 EAp2:Minimum energy performanceposted by Chilufya Lombe on
Hi, we have a project with a certain number of 'back up' systems for air conditioning.
Gross SF Option
CI-2009 EAp2:Minimum energy performanceposted by Sheela I on
Our LEED project boundary includes 20,000 RSF in total . And the core building spaces where no alterations is being done are 1500 SF with in the leed project boundary.
Exterior lighting power density
CI-2009 EAp2:Minimum energy performanceposted by Edwin Wealend on
Hi we are working on a LEED-CI for retail and they have exterior lighting power that doesn't comply with ASHRAE Section 9.4.5 which is compulsory and non-tradeable with interior lighting.
Building Budget Design materials
CI-2009 EAp2:Minimum energy performanceposted by Rodrigo Dias on
Hello again I have another doubt about the Budget Building Design from section 11 of ASHRAE 90.7 – 2007.