CAV - How to meet section 3.1 requirement
CI-2009 EAc1.3:Optimize energy performance - HVACposted by Srimannarayana NCVK on
Hi, For one of my LEED CI project, air distribution is a CAV system. There is a VFD for AHU though. To document EA c 1.3, i need to meet CPG requirement.
Core performance path
CI-2009 EAc1.3:Optimize energy performance - HVACposted by Jatuwat Varodompun on
We plan to option 1 equipment efficiency. 1 We have 500,000+ Btu/h VRF compressor which is specified in CEE Tier two as "NA".
Simulation approach strategy.
CI-2009 EAc1.3:Optimize energy performance - HVACposted by TOMAS URIBE on
Hello Marcus. We have a project that will be applying for LEED certification under CI. The project is located on 4th floor within an office building with 5-floors.
Active controls and thermal control
CI-2009 EAc1.3:Optimize energy performance - HVACposted by Matthew Catterall on
We have a project with both perimeter and interior offices.
LEED CI - Energy Modeling Terms
CI-2009 EAc1.3:Optimize energy performance - HVACposted by SAMY Chamy on
Dear All:- Greetings I need some clarity in terms in the terms used in "LEED ID + C ref guide page no 172" what is meant by 1.Project area 2.Total Segment area of LEED CI project ECB energy s
Option 2: ASHRAE 90.1-2007 Section 11?
CI-2009 EAc1.3:Optimize energy performance - HVACposted by Steve Gross on
Even though the credit language does not state it explicitly, I read "reduce design energy cost compared with the energy cost budget for regulated energy components" to mean "reduce the design ener
Chilled water flow and pipe sizes
CI-2009 EAc1.3:Optimize energy performance - HVACposted by Jayakumar Pamuri on
Hi All, I am here to post my query about chilled water system,flow and pipe sizes.
Option 1
CI-2009 EAc1.3:Optimize energy performance - HVACposted by Azita Mousavi on
I'm working on an existing Building. the original building has its gold certificate CS and all main VAV roof top units are installed originally at 2008.
Portable Air Conditioning.
CI-2009 EAc1.3:Optimize energy performance - HVACposted by Carla Lopez on
Dear all, For an office building project we will be using a PORTABLE AIR CONDITIONER to cool the IT room; the unit has a cooling capacity of 12,000 BTU (Reference: http://www.comfortstarusa.com/pro