Forum quick links
Another CxA Scenario?
NC-2009 EAc3:Enhanced commissioningposted by Christopher Heine on
We have a project over 50,000 sf in DD phase and are in early talks with a potential Facility Manager. Can a FM or a disinterested party from that FM firm serve as a CxA for EAc3?
Energy Modeling with California T24-2008
NC-2009 EAc1:Optimize energy performanceposted by eileen hughes on
Will the GBCI accept the model if it is completed based on Title 24 -2008 energy standard in lieu of the T24-2005 or ASHRAE 90.1-2007?
Flexibility
NC-2009 IDc1:Innovation in designposted by Denise Newbould on
Is it okay to pursue more than one path to obtain ID credits?
Required Signatory IEQp2-1 form?
Schools-2009 IEQp2:Environmental Tobacco Smoke (ETS) controlposted by Joel Register on
On the form for this credit, there is an option to upload IEQp2-RS1.
How to define the "project's energy-related systems"?
CI-2009 EAp1:Fundamental commissioning of building energy systemsposted by Andrew Gil on
I am seeking clarity on this point given the GCBI's June 2011 update of MPRs and the current emphasis on defining a project "in it's entirety".
Existing System with New Chiller Plant
NC-2009 EAp2:Minimum energy performanceposted by Ante Vulin on
Our project is an existing 36,000 sf museum with a planned 18,000 sf addition. The existing portion is served by a dual-duct HVAC system with a boiler and chiller plant.
Walk-off mat system - Stone panels with a recess below.
CS-2009 IEQc5:Indoor chemical and pollutant source controlposted by myriam tschiptschin on
The project team of an office building is interested in using a new product called C/S Floorometry® 401 for the walk off mat: http: //www.c-sgroup.com/files/literature/Floorometry_0.pdf This is a f
LEED CS ID Path 1 - Legally binding performance criteria
CS-2009 IDc1:Innovation in designposted by Caroline Ma on
In our CS project, we would like to develop a legally binding performance criteria for the tenant to attempt 1 point in ID Path 1.
Treatment of District or Campus Thermal Energy and EAp2-7 tables
NC-2009 EAp2:Minimum energy performanceposted by AAME User on
Our project involves the new construction of a healthcare clinic that is being heated and cooled via heating and chilled water produced by a campus central plant.
How to determine the building foorprint?
CS-2009 SSc5.2:Site development - maximize open spaceposted by Gabriela Hernández Castillo on
Our project is a building that literally crosses another building. It consists of a 40 stories building (the LEED building) that comes out of a 3 stories mall (not applying for certification.