Irrigation by hose
NC-2009 WEc1:Water efficient landscapingposted by Marcio Alberto Casado Pereira on
Hi, my project will use non-potable irrigation by hose, but the template of LEED online don't show this option. How can I calculate the efficiency of this method? Thanks in advance
Compliance for SS CR 3 & IEQ CR 3.6
EBOM-2009 IEQc3.6:Green cleaning - indoor integrated pest managementposted by ABHIJIT PISAL on
Our client uses pesticides/chemicals which are allowed to use in India as per local regulation.
Fire Stopping Sealants
NC-2009 IEQc4.1:Low-emitting materials - adhesives and sealantsposted by Mariah Grife on
I am currently tracking the LEED Data for a construction project I am on.
street network
Pilot-Credits PC9:Street Networkposted by Sara Aschliman on
It appears that our project will qualify for this point, and I do believe that the spirit of the credit positively reinforces the walkability of our neighborhood site as the increased intersections
MPR 6 - Energy Star Portfolio Manager not for future buildings?
NC-2009 MPR6:Must commit to sharing whole-building energy and water usage dataposted by Cassandra Kail on
I am currently working on a LEED-NC 2009 Multiple Building Project. We are having a problem with MPR 6; commit to showing whole-building energy and water use data.
definition of greenfield for commercial interiors
CI-2009 SSc2:Development density and community connectivityposted by Ken Dooley on
Hi all, how can a fit-out that is to be certiifed by commercial interiors be a "greenfield development" ? Surely once the core and shell project is completed, the fit-out is on a previously develop
Alternative Compliance Path Case 1: Lease Document
CI-2009 EAc3:Measurement and verificationposted by Carolina Acevedo on
Is there an alternative compliance approach to this credit? My project falls under Case 1 (less than 75% of the project space), but my client owns the floors hence the lack of a lease agreement.
Undefined Outdoor Spaces
CS-2009 SSc6.1:Stormwater design - quantity controlposted by Luis Miguel Diazgranados on
Greetings Everyone I'm working on a office project with outdoor spaces within the LEED Boundary. The project's construction phase is almost finished.
Material-Efficient Framing based on LEED-Homes?
NC-2009 IDc1:Innovation in designposted by Heather DeGrella on
Has anyone tried an ID point for NC, based on the Material-Efficient Framing credit in LEED for Homes?
Determining Baseline for Mixed Use
NC-2009 EAp2:Minimum energy performanceposted by Jason Biondi on
Hi all, thanks for the forum. The building is 8 stories, 3 flrs office, 3 floors parking, 1 retail, 1 resturaunt. Is it accepabable to use the 5 story building baseline schedule if the parking gara