Forum quick links
STC for Ceiling Assembly
Schools-2009 IEQc9:Enhanced acoustical performanceposted by PREMNATH SUNDHARAM on
I'm filling out the Table IEQc9-1 and it asks me for a STC rating for the ceiling assembly. I set the space "adjacent to assembly" to "outdoors " because it is only a 1-story building.
Tenant/Owner Do Not Purchase Food for Occupants...So I Did.
EBOM-2009 MRc5:Sustainable purchasing - foodposted by Michelle Bracewell-Musson on
I have wriiten verification the Tenant (State Office) and Owner do not make food purchases (none for tea/coffee either), therefore, I bought my own UDA Certified Organic and had a the LEED Charrett
Separate Buildings, Same Cellar
NC-2009 MRp1:Storage and collection of recyclablesposted by Jesus Deras on
I have two hotel projects(190K & 98K) which will be filed as two separate LEED projects that have a combined cellar.
LEED Project Boundary in case of uderground parking
Healthcare-v2009 MPR3:Must use a reasonable site boundaryposted by Mario Pinoli on
Hello, just a question about LEED Project Boundary.
Feed-in tariffs
CS-2009 EAp2:Minimum energy performanceposted by BH . on
Hi, Hi, in EU most countries have feed-in-tarriffs, which reimburse the owner for energy produced at a higher rate than the cost of energy.
Ongoing Cx Requirements
EBOM-2009 EAc2.3:Existing building commissioning - ongoing commissioningposted by Colleen Collins on
I have a question regarding EA2.3 As I understand it, it appears that the ongoing Cx process effectively begins with EAc2.1 and EAc2.2.
EA prereq documentation
NC-2009 EAp2:Minimum energy performanceposted by Mike Decoster on
We have documented EA prereq 2. We are using LEED NC v 2009 and we are using form version 4. We have filled in all the required information with the exception of the Target Finder.
Mixed Ventilation
NC-2009 IEQc2:Increased ventilationposted by Paula Hernandez on
Hello Everybody, I have this Project, which main activity is store and move packages.
LEEDUser vs. USGBC
Pilot-Credits PC34:Design for Adaptabilityposted by Nicholas Swinehart on
There are discrepancies between the LEEDUser and USGBC requirements for this pilot credit.
MPR 2 - Separate Ownership
NC-2009 MPR2:Must be a complete, permanent building or spaceposted by Jonathan Weiss on
I am curious about the separate function AND ownership requirement for an addition to a non-certified building.