New vs. Recycled Wood
CI-2009 MRc7:Certified woodposted by Kevin Dunham on
Is paint-grade molding (made from short pieces finger-jointed together to form a usable length) considered new wood or recycled wood (presumably 100% pre-consumer)?
Bi-weekly Inspections - must be done by??
EBOM-2009 IEQc3.6:Green cleaning - indoor integrated pest managementposted by Michelle Bracewell-Musson on
The Plan requires biweekly inpections: 'Visual inspections shall be performed at least 2 times per month, with treatment if necessary.
Compliance for LEED, ASHRAE 62.1. Ventilation System controls
NC-2009 IEQp1:Minimum indoor air quality performanceposted by JOSE R. TAGLE on
To meet the minimum requirements from section 4 to 7 of ASHRAE 62.1-2007, we must comply with section 5.4 "Ventilation System controls", and for this we should include controls that enable system t
LEED Heatlhcare - FTE Calculation
NC-2009 PIf3:Occupant and Usage Dataposted by Craig Pryde on
We are working on a new MOB with 4 of 6 tenant suites being completed at the same time as shell/core.
Racking system in warehouse
CS-2009 MRc5:Regional materialsposted by Jean-Baptiste Noel on
In a C&S warehouse project, I was wondering whether the racking system could be counted in the materials list (as long as put consistently in all MR credits of course)? I am not including the f
SSc2 option 2
CI-2009 SSc2:Development density and community connectivityposted by Mike D on
Pursuing Option 2 for this credit, the new version of the form asks for the development density of the surrounding residential zone or neighbourhood.
LEED Health Care 2009 MR Prerequisite 2: PBT Source Reduction
Healthcare-v2009 MRp2:PBT source reduction - mercuryposted by William Kelly on
For Uload L-14 providing calculations for collection space and projected waste: 1.
Preferred Parking for CS?
CS-2009 SSc4.4:Alternative transportation - parking capacityposted by Ellen Mitchell on
I have always assumed that this credit was pretty much the same for NC and CS projects - specifically that we must not exceed code minimum AND provide preferred parking for carpooling vehicles for
purchased heat pumps for ASHRAE 90.1
NC-2009 EAp2:Minimum energy performanceposted by Jean Marais on
Dear Group, As you know additional requirements from LEED led to purchased heat water coils being substituted for furnis heat coils in some unitary systems.
Upper and lower roof
Healthcare-v2009 SSc7.2:Heat island effect - roofposted by BABAR MEHMOOD on
There is a small pump room designed on the roof top.