District / Campus Energy - Modeling Option 2 (Full accounting)
NC-2009 EAp2:Minimum energy performanceposted by Maya Karkour on
Dear All, I am intending to model a building on campus which is connected to a campus energy system providing chilled water and hot water.
Elevator Machine Room/ Electrical Room Ventilation?
NC-2009 IEQp1:Minimum indoor air quality performanceposted by Xun Jia on
Does elevator machine room or electrical room need to comply with ASHRAE 62 for Ventilation?
trickle vents in apartments
NC-2009 IEQp1:Minimum indoor air quality performanceposted by Courtney Royal on
How do you document if there are trickle vents in the apartments?
Existing landscaping, including turf, and no irrigation
NC-2009 WEc1:Water efficient landscapingposted by Lew Bonadies on
We're renovating an Army barracks, with minimal changes to the existing landscaping, which includes turf. The landscaped area exceeds 5% of the site area.
Preferred Parking on two different garage floors
CS-2009 SSc4.3:Alternative transportation - low-emitting and fuel-efficient vehiclesposted by Loreana Marciante on
On our project all the parking is underground. Rather than placing all preferred spots on one floor we would like to stack them over two floors close to the parking elevator.
VRV System
CI-2009 IEQp1:Minimum indoor air quality performanceposted by SW LEE on
Hi, My project is using VRV system for cooling.
Required signatories of whom?
NC-2009 EAp2:Minimum energy performanceposted by Ricardo Sá on
In the newest version (v4) of the LEED forms and specifically on the form for this credit there are several required signatories, however, there isn't any information regarding of who is supposed t
Eligibility of PV systems receiving SRECs
NC-2009 EAc2:On-site renewable energyposted by Adam Prince on
I apologize if this was covered explicitly in another discussion. In Massachusetts, there's a well-established SREC market.
Existing systems modeling
NC-2009 EAp2:Minimum energy performanceposted by Tiffany Moore on
If a project retains existing mechanical systems, but the overall scope of the renovations meets the new construction threshold, are the baseline calcs based on code-minimum or should the project a
Sidewalk clarification
Pilot-Credits PC14:Walkable Streetsposted by Michelle Oishi on
One of the requirements states, "At-grade crossings with driveways account for no more than 10% of the length of sidewalks within the project".