waste management by bedroom vs sf

Homes-v4 MRc3:Construction waste management
posted by  Elizabeth Eason  on 

LEED v4 for homes Table 1:Baseline Waste list waste by both bedrooms and conditioned space but there is no guidance as to when one should use conditioned sf vs bedrooms.

1
Tue May 9, 2017, 5:32 pm

Treated (rain) water for human contact...

NC-2009 WEc2:Innovative wastewater technologies
posted by  Jorge Lopez de Obeso  on 

Here is a situation: Rain water is captured and treated for reusing to flush and flow fixtures. A single cistern storages both rainwater and municipal water supply.

1
Tue Feb 4, 2014, 8:39 pm

72 Hour Universal Notification conflicts with weather patterns?

EBOM-2009 IEQc3.6:Green cleaning - indoor integrated pest management
posted by  Heather DeGrella  on 

I'm working with a Community College that has numerous campuses in the Portland, Oregon area to submit IEQc3.6 as an ID credit for LEED NC.

1
Thu Jan 23, 2014, 2:47 pm

Pilot Credit 34 Update

Pilot-Credits PC34:Design for Adaptability
posted by  Sandy Chung  on 

Be sure to use the Updated version 8/1/2011. The required features are in line with the California Building Code Accessibility requirements.

0

Subtracting built-in furniture/casework from square footage

EBOM-2009 IEQp1:Minimum indoor air quality performance
posted by  American University  on 

We've had a designer tell us that built-in furniture and case work (like a fan-coil unit enclosure) can be deducted from the square footage of a room when calculating the window opening requirement

1
Thu Jan 23, 2014, 9:28 pm

Site Lighting for Campus Plan

CS-2009 EAp2:Minimum energy performance
posted by  charles bell  on 

Hello, We have a campus application for our 3 mixed-use buildings. We are now on our final review and need to modify our submittal.

1
Fri Jan 24, 2014, 3:02 pm

Help with table G3.1.1A,B

CS-2009 EAp2:Minimum energy performance
posted by  charles bell  on 

The project consists of non residential building of 6 stories.

1
Fri Jan 24, 2014, 3:13 pm

Recertification - Changed Cleaning Contractors

EBOM-2009 IEQc3.4:Green cleaning - sustainable cleaning equipment
posted by  Greengrade User  on 

For a recertification, if the building management switches cleaning contractors partway through the performance period, and now completely different cleaning equipment is being used at the building

1
Thu Feb 6, 2014, 11:19 pm

Blue Roof

NC-2009 SSc6.1:Stormwater design - quantity control
posted by  Jamison Hill  on 

As part of NYC's blue roof requirement, roofs must provide 24 hour detention detention for the 2-yr design storm and an equivalent peak runoff rate equal to a curve # of approx 50 for projects disc

1
Thu Jan 23, 2014, 10:40 pm

Core and Shell minimum occupancy

NC-2009 MPR5:Must comply with minimum occupancy rates
posted by  Vada Kornegay  on 

It seems clear but, to be certain, can a core and shell project have an occupancy of less than 50%?

1
Fri Jan 24, 2014, 4:38 am