Hi, we are working on getting the verbiage of the lease correct.
FTE calculation
NC-2009 PIf3:Occupant and Usage Dataposted by Stella Stella on
I have a project where the occupants work on a 12 hour shift. The office is occupied by 97 occupants at 1 shift. So is my FTE = 97 X 12/8 = 145.5? Thanks in advance.
Project has all 5 Categories
Schools-2009 WEc4:Process water use reductionposted by Sara Zoumbaris on
Hi all, My project has all 5 categories installed (dishwasher with racks, pre rinse etc..), however one of the products is above the maximum limit.
Designated Drop-off spaces
Schools-2009 SSc4.3:Alternative transportation - low-emitting and fuel-efficient vehiclesposted by Matthew Heaton on
Can all preferred parking spaces for low-emitting and fuel-efficient vehicles also be carpool drop off spaces.
The year of metering
EBOM-v4 EAp2:Minimum energy performanceposted by Vindio Corro on
Must be the year of metering after the registration of the project or can be used a year of metering of before?
Does all of Section 1.6 results have to be filled?
NC-2009 EAp2:Minimum energy performanceposted by Ivan Priatman on
Dear LEED, We are trying to achieve points in EAp2 scorecard via Building Simulation Method.
Duct sealing methods
NC-2009 IEQc5:Indoor chemical and pollutant source controlposted by John Covello on
Hello, Can alternative methods for duct sealing be used besides plastic wrap? One of our contractors is proposing using foam to seal the end of the duct openings.
Gravel nonroof area
NC-2009 SSc7.1:Heat island effect - nonroofposted by Charalampos Giannikopoulos on
Under what circumstances could a nonroof area covered with light gravel be considered as non-hardscape?
Car Park Ventilation Fan Energy Savings
NC-2009 EAc1:Optimize energy performanceposted by Chilufya Lombe on
Hi, on a recent project we were requested to provide evidence that 5 buildings built within the last three years did not have carbon monoxide sensors installed in the basement car parks in order to
No exposed soil - how to comply with ESC?
NC-2009 SSp1:Construction activity pollution preventionposted by Michael E. Edmonds-Bauer on
We have a small project that consists af an existing one level building that will have an major renovation.