Forum quick links
Monitoring Period
Pilot-Credits EApc65:Monitoring based commissioningposted by Mari Hamasaki on
What is the required monitoring period for this credit?
What is the difference
NC-2009 IEQp1:Minimum indoor air quality performanceposted by John Pugh on
What is the difference between breathing zone outdoor airflow and room outdoor airflow rate? How do I find the room outdoor airflow rate for bedroom/living room type spaces Thanks.
Reduction of impervious area
NC-2009 SSc6.2:Stormwater design - quality controlposted by Danielle Spicer on
I have a project where we are promoting infiltration by installing permeable pavers for a portion of the pavement, and we are capturing and treating runoff from 90% of the average annual rainfall e
audit of land-fill materials only?
EBOM-2009 MRc6:Solid waste management - waste stream auditposted by Jutta Berns on
our hotel project already has in place a rigorous waste diversion programme, where 80%+ is diverted from landfill.
Flush-Out Requirement for a Naturally Ventilated Building
NC-2009 IEQc3.2:Construction IAQ management plan - before occupancyposted by Eric Carbonnier on
The project is an 8 story residence hall on a university campus. The building is not equipped with a central ventilation system and dorm rooms rely on natural ventilation.
Steel extraction location
NC-2009 MRc5:Regional materialsposted by Tiffany Moore on
I feel like broken record on this topic, because I know I've been through this before.
Pre-Owned furniture
CI-2009 MRc4:Recycled contentposted by Susan Di Giulio on
If a project is using less than 30% of the furniture budget's worth of pre-owned furniture, and thus not attempting MRc3.2, can that be used towards MRc4 instead?
SRI required testing amounts
NC-2009 SSc7.2:Heat island effect - roofposted by Anna Korinkova on
Hello, could anybody tell me how we can state the number of SRI tests on a project? We intend to place gravel on the roof and provide a concrete parking log.
Workspace opens to exterior and interior
NC-2009 IEQc5:Indoor chemical and pollutant source controlposted by Peter Doo on
We have a project that includes a workshop/studio space.
Parking Garage above Non LEED Building
Healthcare-v2009 MPR3:Must use a reasonable site boundaryposted by Kar Kerman on
I'm not sure whether I can (or should) include a parking garage in a project I'm working on. The parking garage is located in an adjacent building and has a separate owner.