Commissioning Requirements Off-site

Credit Forums
posted by  Alicia Villanueva  on 

Dear all, We are choosing to follow the option of off-site space but funded by the project for this credit. The location is an existing building near the project site.

0

2009 calculator - "private" bathrooms in a commecial facility

EBOM-2009 WEp1:Minimum indoor plumbing fixture and fitting efficiency
posted by  Jessica Hawley  on 

I have mulit-story office building where the first floor has only one "private" bathroom for guests of the building to use in the lobby.

1
Sun Mar 22, 2015, 10:51 am

CORE area and SHELL area

CS-2009 IEQc4.1:Low-emitting materials - adhesives and sealants
posted by  Yodi Danusastro  on 

How to specify the IEQc 4.1 credit area limit for CS in SHELL area? in case for tenant spaces (that is still unoccupied), or the anchor tenant that has construction in parallel.

1
Mon Mar 30, 2015, 1:17 am

Baseline for Blow-out Fixtures

CS-2009 WEp1:Water use reduction
posted by  study topenergy  on 

According to the Water Use Reduction Additional Guidance (April 2013), when selecting the "Blow-out fixture" option, the 3.5 gpf baselne should also be used for the installed case.

1
Mon Nov 30, 2015, 10:53 pm

Non recyclables in recycling stream

EBOM-2009 MRc6:Solid waste management - waste stream audit
posted by  Vanessa Seibert  on 

I think I know the answer but just want to double check.

1
Tue Mar 24, 2015, 8:04 pm

Parking space ownership

CS-2009 SSc4.3:Alternative transportation - low-emitting and fuel-efficient vehicles
posted by  Gustavo De las Heras Izquierdo  on 

I see this credit mainly oriented to shopping malls and office buildings, but how should I address a project where all parking spaces are going to be SOLD to individual owners?

1
Thu Mar 26, 2015, 1:10 am

Parking spaces owned

NC-2009 SSc4.3:Alternative transportation - low-emitting and fuel-efficient vehicles
posted by  Gustavo De las Heras Izquierdo  on 

I see this credit mainly oriented to shopping malls and office buildings, but how should I address a project where all parking spaces are going to be SOLD to individual buyers?

0

Target Finder: Design vs Target

NC-2009 EAp2:Minimum energy performance
posted by  Rock Ridolfi  on 

All, new to energy modeling and reviewing the EAp2 online template trying to figure out the required inputs and reports for the Target Finder section, Design vs Target.

1
Thu Mar 26, 2015, 12:44 am

LEED "Owner" (vs. Leasing)

Retail-NC-v2009 PIf3:Occupant and Usage Data
posted by  Serena Wray  on 

I am working with a national retailer who controls the design of their own stores and all LEED decisions that are made regarding those stores.

1
Wed Mar 23, 2016, 4:17 am

Total material cost

NC-2009 MRc5:Regional materials
posted by  Sahar Abi-Ziki  on 

Hello, In our project, we decided to estimate real total material cost without equipments and labor for division 2-10. What kind of proof the contractor needs to present in this case?

1
Fri Nov 27, 2015, 7:41 pm