Canopy to building with wall opening (is it a "complete bldg")?

NC-2009 MPR2:Must be a complete, permanent building or space
posted by  John Lee  on 

We have a project that is an existing canopy converted into a building without a 15' wide wall on one side. There will be a 10'x15' enclosed office inside this building.

1
Fri Nov 27, 2015, 3:52 am

flush out possible by phase

NC-2009 IEQc3.2:Construction IAQ management plan - before occupancy
posted by  Sahar Abi-Ziki  on 

Hello the first phase (parking garage) of our project will be delivered to client for occupancy now, but the rest of the project will still be under construction for a while.

1
Tue Jan 12, 2016, 3:21 pm

43" partitions block views and negate compliance?

EBOM-2009 IEQc2.4:Daylight and views
posted by  Vanessa Seibert  on 

I see that there was some conversation on the views credit back in 2011.

1
Tue Dec 1, 2015, 2:29 pm

1 VAV 2 offices, one restroom

NC-2009 IEQc6.2:Controllability of systems - thermal comfort
posted by  Saju Varghese  on 

Hello. I have a question regarding the controllability of thermal comfort for 2 offices.

0

Sub-merters

EBOM-v4 EAp2:Minimum energy performance
posted by  Ann-Judith Belanger  on 

Hi, we have a building that share some mechanical equipment with the adjacent building.

1
Thu Sep 24, 2015, 5:33 pm

treat wastewater to teriary standards?

NC-2009 WEc3:Water use reduction
posted by  Erin Holdenried  on 

I have a project that is pursuing WEc2 via Option 2 treating wastewater to tertiary standards and infiltrating onsite through landscape irrigation. Can this factor into water saving for WEc3??

1
Fri Nov 27, 2015, 7:33 pm

Recording the recycling of "whitegoods"

NC-2009 MRc2:Construction waste management
posted by  Neumann Monson  on 

In an effort to achieve a 95% diversion rate, my team will be submitting waste receipts for the demolition of two buildings that existed on our site before construction of the new project began.

1
Thu Sep 3, 2015, 5:11 pm

Definition of Main Building Entrance

NC-2009 SSc4.1:Alternative transportation - public transportation access
posted by  Annalise Reichert  on 

I am working on a project that has a main lobby entrance and another side entrance.

1
Fri Sep 4, 2015, 1:08 am

Low Flow Sink

CI-2009 WEp1:Water use reduction
posted by  Ray Jones  on 

All, Is a break room sink in an office space considered a kitchen sink with a 2.2 gal/min baseline or a commercial lav with a .5 gal/min baseline?

1
Mon Sep 7, 2015, 1:12 am

Parking garages

CI-2009 SSc2:Development density and community connectivity
posted by  Eric Thompson  on 

For Option 1 / Development Density - we have several large parking garages within our radius. Am I correct in thinking these would not be counted?

1
Sun Dec 6, 2015, 11:18 pm