Checking ESC plan at design stage?
NC-2009 SSp1:Construction activity pollution preventionposted by Hrvoje Kvasnicka on
Hi All Since this is a prerequisite which forms part of construction stage submittal, I was wondering if it there is a way to have the ESC plan reviewed by GBCI at design stage.
FSC Controlled Wood
CI-2009 MRc7:Certified woodposted by Maory Sciubba, LEED AP on
Good morning all, I am positive that I read somewhere that FSC Controlled Wood does NOT contribute to the certified wood point.
Open Office Landscape and System Furniture
NC-2009 IEQc8.2:Daylight and views - viewsposted by Raina Tilden on
Hi everyone, I have read ever post on this forum twice now, and I am still confused!
Signatory requirements ( Does engineer need to be PE ? )
NC-2009 EAp2:Minimum energy performanceposted by Matt Dem on
Shall the person who enters his/her initials under signatory section ( for example EAp2-1, 2-2, 2-3 ) be registered mechanical engineer (PE) ?
Table 1.4.7B Entering Outdoor Airflow in Baseline
NC-2009 EAp2:Minimum energy performanceposted by Vassil Vassilev on
Greetings, There is a clarification issue while entering these values in the Baseline about which I'd appreciate some advice. The OA flow should be identical in both models.
How to prove compliance with Mechanical Ventilation
NC-2009 EAp2:Minimum energy performanceposted by Praveenbabu Rajkumar on
The project is a medium sized workshop shed and will be mechanically ventilated with fans with a particular air change per hour as per the local standards.
Does energy model should include walls to be consistent w/ Plf2
NC-2009 EAp2:Minimum energy performanceposted by Matt Dem on
I am working on a project (2 story office building) as a LEED AP & architect and received Preliminary Design Package comments from GBCI.
Hot-Rolled Structural Steel - MRc4 Products
NC-2009 MRc4:Recycled contentposted by Robert East on
I am working as part of a Q.A. team at an Integrated Steel Complex in the Middle East which operates 3 core manufacturing plants; 1. Direct Reduction Plant producing Direct Reduced Iron (DRI); 2.
Ice-cream factory with sub-zero working conditions
NC-2009 IEQc7.1:Thermal comfort - designposted by André Harms on
Good day, The project I'm working on is an ice-cream factory which will have staff working for short spells (but more than 15min) in spaces cooled to down to -40C.
New Construction vs Major Renovation
NC-2009 EAp2:Minimum energy performanceposted by Ritwik Kakati on
Our project consists of renovation of 140,000 SF of an existing building, as well as the addition of 30,000 SF of new space.