NC-2009 MRc4:Recycled contentposted by Nicholas Klever on
I have input all of the information into the form table for these Materials and Resources credits, but the table indicator at the bottom of the table still reads "Incomplete".
Fixture Usage Group
NC-2009 WEp1:Water use reductionposted by Mike D on
Hi, The project has male and female restrooms with urinals in the male restrooms, as well as unisex restrooms without urinals in the basement and ground levels.
EAp2 Form
CS-2009 EAp2:Minimum energy performanceposted by Lily Li on
in EAp2 Form Summary shows "N", but no error information provided, is this Form wrong?
Discrepancy in graywater volume between Engineer & ELED
NC-2009 WEp1:Water use reductionposted by Maya Karkour on
Dear all, We are consulting for a big retail shopping mall.
Sampling Locations
NC-v4 EQc4:Indoor air quality assessmentposted by Courtenay Griffin on
Recognizing the issues already under discussion regarding the analytical methods and the maximum contaminant levels presented in LEED v4...
Continuous insulation - Interrupted by slab vs truly continuous
NC-2009 EAp2:Minimum energy performanceposted by Victoria Watson on
Hi, I am modeling a masonry building.
Natural Ventilation in a Warehouse
EBOM-2009 IEQp1:Minimum indoor air quality performanceposted by Diego Pietzsch on
How can a large Warehouse that uses natural ventilation system, but does not meet the requirements of ASHRAE 62.1-2007 section 5.1 be able to pass under the LEED EBOM IEQp1?
100% OA multiple-zone system
NC-2009 IEQp1:Minimum indoor air quality performanceposted by Michael Wironen on
Hi, I'm a little confused about a review comment we received. We have rooftop AHUs supplying 100% Outdoor Air to multiple zones equipped with terminal fan coil units.
What does "can include" mean?
Healthcare-v2009 MPR3:Must use a reasonable site boundaryposted by Aron Weis on
If there is a non-LEED-certifiable building within the LEED project boundary, the project team can include the non-certifying building within the project boundary in ALL relevant submittals that ar
Appendix 4 - Case A
CS-2009 WEp1:Water use reductionposted by Sy Shumaker on
We have a CS project with no signed tenants yet. The owner is providing central restrooms and showers for all of tenants in the base CS project.