Initial energy model required for M&V?
NC-2009 EAc5:Measurement and verificationposted by Eamon Geary on
I am working on a large campus project. We are planning on obtaining EA 5 for all eight facilities on the campus. However, we are not doing energy models for all eight facilities.
Existing Building Envelope Wall
NC-2009 EAp2:Minimum energy performanceposted by Matt Humphreys on
Project background: The project owner has purchased an unconditioned warehouse with the intent to convert it 100% into a school.
Tennant Space Layout
CS-2009 EAp2:Minimum energy performanceposted by Matt Humphreys on
The LEED reviewer for a Core and Shell Office Building has requested the design team to illustrate a hypothetical layout of the tenant spaces to document the potential for Daylighting/Views credits
Using the 62MZ calculator
EBOM-2009 IEQp1:Minimum indoor air quality performanceposted by Christina Reeves on
Hello, I have two questions from our ME about using the spreadsheet calculator: 1. Neither of us can get the macros to work on the calculator - to add zones, etc.
Can PEFC Certification replace FSC Certification
EBOM-2009 MRc1:Sustainable purchasing - ongoing consumablesposted by David ESPAGNET on
Hello everybody, The main question is in the tittle.
Climate zone in Copenhagen, Denmark
NC-2009 EAc1:Optimize energy performanceposted by Lise Dannesboe on
Our office building is placed in Copenhagen, Denmark. Our question is which climate zone to use?
pipe insulation
NC-2009 EAp2:Minimum energy performanceposted by Francesco Passerini on
If I model a hydronic HVAC plant shall I consider in the proposed model the heat losses through the pipes? And in the baseline model?
No contaminant area-related-sources
NC-2009 IEQp1:Minimum indoor air quality performanceposted by Ian McCall on
Dear LEED Users, I have a question regarding the prerequisite 1 of IEQ Section: Minimum Indoor Air Quality Pollution. According to the Ventilation Rate Procedure of ASHRAE Standard 62.1-2007, the
Eap2. Fan Power Limitation Pressure Drop Adjustments.
NC-2009 EAp2:Minimum energy performanceposted by Carlos Vazquez on
We are in process of submitting for certification a health care out patient clinic. The proposed buiding has air handling units are chilled water cooled with many devices.
Credit requirement clarification.
Healthcare-v2009 SSc9.1:Connection to the natural world - places of respiteposted by BABAR MEHMOOD on
We are working on a healthcare out patient clinic. The credit says that we will take the net usable area excluding the building equipement, vertical circulation and structure.