Forum quick links
water treatment outside LEED project boundary
NC-2009 WEc2:Innovative wastewater technologiesposted by Adi Negara, LEED AP BD+C on
Dear all, We have a small LEED project (an office space with landscape) which located inside non-LEED construction project (factory), which will be conducted simultaneously.
Lighting in kWh?
CI-2009 EAc4:Green powerposted by Maria Porter on
The answer to this one might be obvious, but I just can’t see it: EAc4 form says to “Provide numbers that correspond with the information provided in EAp2 and EAc1.3”.
How long must we follow thru on erosion control log?
NC-2009 SSp1:Construction activity pollution preventionposted by Donald Bauman on
Our building and site is complete except for the grass. It was hydro-seeded last week but the grass that has taken is less than 75%.
the area meet the requrement must the same area?
CS-2009 IEQc8.1:Daylight and views - daylightposted by Shenhao Li on
Hi guys Please help me solve below three question 1.LEED Guidance required 75% of all regularly occupied spaces meet the daylight requirements at both 9 a.m.
Filtering requirements
NC-2009 SSc6.2:Stormwater design - quality controlposted by Mike D on
If we capture rainwater and reuse it for irrigation, do we need to show any type of filtering or will this automatically acquire the credit?
PI Form 3 occupancy question, transient student vs retail
NC-2009 PIf3:Occupant and Usage Dataposted by Mike Stopka on
Hello I am submitting for a Multi-Family Residential apartment tower. It has retail space at the ground level.
Remediation prior to project start date
NC-2009 SSc3:Brownfield redevelopmentposted by Lauren Fakhoury on
Does anyone know if LEED defines a project start date for this credit? I am working on a project where there was some ACM identified and abated back in 2009.
Existing Building vs. New Construction
NC-2009 EAc1:Optimize energy performanceposted by Jenelle Shapiro on
I am working on a project in Tokyo, Japan. They are considering saving part of the exitsing building structure for multiple reasons.
the minimum efficiency for the baseline case PTACs
CS-2009 EAp2:Minimum energy performanceposted by tiantian zhou on
Dear sir, Our LEED review of EAp2 said that the minimum efficiency for the Baseline Case PTACs should be 9.3 EER. I cannot understand it clearly and find the corresponding terms in 90.1.
Pilot credit 80 requirements are not clear
Pilot-Credits MRpc80:Environmentally preferable interior finishes and furnishingsposted by Helen Kessler on
The Pilot credit requirement is as follows: "Use at least 5 different third party certified products which account for at least 50% of the total interior finishes and furnishing materials by cost.