One stop with 6 different rutes - Expemplary Performance

CS-2009 SSc4.1:Alternative transportation - public transportation access
posted by  Gabriela Hernández Castillo  on 

Our project is located on a heavily dense area and in one of the major streets. There is two bus stops that are within the .25 radius, but both bus stops are served by the same rutes.

2
Integrated Design & LEED Specialist
SERA Architects
LEEDuser Expert
1361 thumbs up
Thu Apr 18, 2013, 5:07 pm

Able to use a calculator other than USGBC's?

NC-2009 MRc4:Recycled content
posted by  Andrew Tse  on 

Does GBCI now require sole use of USGBC's calculator for MRc3-7? Or is it allowing use of 3rd-party calculators such as from LEEDuser or GCs?

4
Thu Apr 18, 2013, 3:32 pm

Registered LEED project on Hold?

NC-2009 PIf2:Project Summary Details
posted by  Hugh Hagues  on 

Hi, my LEED project is registered and I understand I have a time limit to complete my LEED documentation & projects.

2
Thu Apr 18, 2013, 12:20 pm

Semiheated Walls

NC-2009 EAp2:Minimum energy performance
posted by  Jean Marais  on 

I've interpreted the semiheated column in table 5.5-1 refering to the external walls of a semiheated space...as this table is much conserned with the envelope (the partition between the semiheated

5
b.i.g. Bechtold DesignBuilder Expert
LEEDuser Basic Member
581 thumbs up
Thu Apr 18, 2013, 11:23 am

Mechanical room covered by greenroof

CS-2009 SSc7.2:Heat island effect - roof
posted by  Michael E. Edmonds-Bauer  on 

By definition the mechanical room will be excluded from roof calculations. However, we are considering covering a mechanical room with a greenroof in order to apply for this credit.

2
Founder & Community Director
Metricorps
LEEDuser Expert
7784 thumbs up
Wed Apr 17, 2013, 9:54 pm

Hotel Spa Water Use - LEED NC

NC-2009 WEp1:Water use reduction
posted by  Ian McCall  on 

I am working on a high-end hotel that has a spa installed. Is the spa considered in the water use reduction calculations or is it considered process as water? Thank-you

3
Environmental Engineer
LEEDuser Basic Member
11 thumbs up
Wed Apr 17, 2013, 7:52 pm

Several issues on PI FORM 2

NC-2009 PIf2:Project Summary Details
posted by  Albert Sagrera  on 

Hi!! Do parquing areas for bicycles also be excluded from "Total gross square footage"? When in PIFORM 2 LEED asks "Number of stories below grade, excluding parking:", in our case we have a floor

3
Default Avatar
Architect
Societat Organica
LEEDuser Basic Member
11 thumbs up
Wed Apr 17, 2013, 7:32 pm

Play ground equipment

Schools-2009 MRc4:Recycled content
posted by  Ameet AA  on 

Is it prudent to include the Play ground equipments into the following LEED credit calculations?could anyone please share their experience in dealing with playground equipments for LEED compliants?

5
Default Avatar
LEEDuser Expert
472 thumbs up
Wed Apr 17, 2013, 5:11 pm

How do GBCI reviewers interpret the limits of ASHRAE 55?

NC-2009 IEQc7.1:Thermal comfort - design
posted by  Lindsay Austrom  on 

I just re-read Nadja Turek's earlier comment (from Aug 29, 2012) which included this excerpt from a CIR response: "The metabolic rate for occupants involved in highly physically activity fall outsi

2
Building Performance Analyst
The Green Engineer
LEEDuser Premium Member
11 thumbs up
Wed Apr 17, 2013, 3:54 pm

Furniture salvaged from site=Regional Mat+diverted Const. Waste?

Schools-2009 MRc5:Regional materials
posted by  Renee Shirey  on 

We will be salvaging furniture from a school already on our site, but we are not going for MR3 (Mat. Reuse) due to the limited amount.

6
Default Avatar
Built Environment Professional
Built Kansas City LLC
LEEDuser Basic Member
28 thumbs up
Wed Apr 17, 2013, 2:46 pm