Sharing "designated" exhaust systems
NC-2009 IEQc5:Indoor chemical and pollutant source controlposted by Iris Amdur on
Can a project provide one shared exhaust system for two hazardous gas/chemical use areas? Or to comply with the term "designated" does each space needs its own exhaust system?
Breathing Zone definition
NC-2009 IEQp1:Minimum indoor air quality performanceposted by Gabriel Moreno on
Hello everyone, I'm confused by a substantial discrepancy between two different definitions that I have come across in regards to Breathing Zone. 1) LEED Definition: "The breathing zone is the re
date stamped photos
NC-2009 SSp1:Construction activity pollution preventionposted by Mike Decoster on
LEED online requests the following: Provide date-stamped photos showing the measures taken, including any corrective action, to effectively implement the ESC plan.
Roofing Adhesives, Sealants & Mastics
NC-2009 IEQc4.1:Low-emitting materials - adhesives and sealantsposted by Catherine Blakemore on
I am reviewing a LEED submittal for roofing adhesives, sealants and mastics. 1. I am unsure of the categories each primer. Can you help? 2.
VRF HVAC Compliance
Schools-2009 IEQp3:Minimum acoustical performanceposted by Ben Thompson on
We are using a VRF HVAC System at a PK-8 School in Alexandria.
Shading by building and trees
NC-2009 SSc7.1:Heat island effect - nonroofposted by Terry Jordahl on
To come up with an area of shaded parking, etc, do I just add up the totals of my 10AM Noon and 3PM shadings by trees and buildings?
Modeling District Cooling / Heating
NC-2009 EAc1:Optimize energy performanceposted by Maya Karkour on
Dear All, I've been reading through the details of modeling a district heating / cooling plant, and it seems rather complicated!
Educational Program - Case Study
NC-2009 IDc1:Innovation in designposted by Eamon Geary on
One of the components of an Educational Program ID credit is a case study.
Topsoil
NC-2009 SSp1:Construction activity pollution preventionposted by Ameet AA on
Could anyone please advise, whether the project would fail to achieve the SSp1: Construction Activity Pollution Prevention, if approx.
Annual Weather Normalized Source Energy Intensity
EBOM-2009 EAp2:Minimum energy efficiency performanceposted by Stefanie Hoffmann on
Hi all, We’re working on an EBOM Project in Finland (Educational Building) and are about to fill in the Case 2 Calculator for EAp1 (Option1 Tab).