LEED MV Credits compliance with Option D

NC-2009 EAc5:Measurement and verification
posted by  Ameet AA  on 

To achieve this credit, during the CONSTRUCTION Stage we just have to submit the IPMVP-OPTION D compliant Measurement and Verification Plan together with Diagram showing the locations of any meter

2
Mechanical Engineer
Integral Group
LEEDuser Expert
342 thumbs up
Tue May 15, 2012, 4:49 pm

shading for 5-6 storey building

CS-2009 EAc1:Optimize energy performance
posted by  charles bell  on 

Can shadow/shading from adjacent buildings be factored into our program model?

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4461 thumbs up
Mon May 14, 2012, 9:15 pm

Naturally Ventilated Garment Factory for 90.1 appendix G

NC-2009 EAp2:Minimum energy performance
posted by  Kevin Sullivan  on 

We are looking to certify a garment factory in Dhaka which will not have any conventional HVAC systems.

9
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4461 thumbs up
Mon May 14, 2012, 5:42 pm

documenting uneven male/female occupancy

NC-2009 WEp1:Water use reduction
posted by  Marni J Evans  on 

Hello All, Can you please provide your insight?

12
Mon May 14, 2012, 1:09 pm

Residential Kitchen Sink / Kitchen Sink / Public Lavatory Faucet

NC-2009 WEp1:Water use reduction
posted by  Udana Ratnayake  on 

We are working in a hotel project where no kitchen sinks have been installed in guest rooms. guests come to restaurants within hotel premises to take meals.

2
Mon May 14, 2012, 11:56 am

Outdoor Airflow Measurement with constant volume ventillation

EBOM-2009 IEQc1.2:Indoor air quality best management practices - outdoor air delivery monitoring
posted by  Michael Smithing  on 

Our building measures the outdoor airflow at the AHU. As we have a constant volume system (fan-coils) with 100% fresh air, from that point onward the airflow is not varied.

3
THREE Consultoría Medioambiental
LEEDuser Basic Member
1 thumbs up
Fri May 11, 2012, 6:58 pm

Changing CxA agents after Final Design

NC-2009 EAc3:Enhanced commissioning
posted by  Elle Brown  on 

Due to issues with the contract and how our project was funded, we may be forced to get a new CxA to continue the project after final design.

3
Fri May 11, 2012, 6:24 pm

Which area type should be considered for simulation?

CS-2009 EAc1:Optimize energy performance
posted by  Fabiano Castro  on 

A question has been raised regarding which space area (GROSS or NET) should be considered into the simulation thermal blocks conception in order to result in the most accurate results.

4
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4461 thumbs up
Thu May 10, 2012, 4:56 pm

Low VOC content for treated wood products

NC-2009 IEQc4.1:Low-emitting materials - adhesives and sealants
posted by  Matthew Perna  on 

Are preservative-treated and fire-treated wood products exempt from this credit since the treatment is done off-site?

4
CEO
Green Commons, LLC
LEEDuser Expert
586 thumbs up
Thu May 10, 2012, 4:47 pm

Furniture/systems furniture use in IEQc8.1

NC-2009 IEQc8.1:Daylight and views - daylight
posted by  Tiffany Moore  on 

I've been trying to find a confirming statement that either includes or excludes furniture/systems furniture from the daylight calculations of IEQc8.1, but have not been successful.

2
Director of Sustainability
DBR Engineering Consultants
LEEDuser Basic Member
244 thumbs up
Wed May 9, 2012, 7:26 pm