Condensate meters
EBOM-2009 WEc1:Water performance measurementposted by Andrea Marzullo on
1. Is anyone using condensate for make-up to their cooling tower? 2. If so, what size and type of meter is being used? 3.
Standard path vs alternative compliance approach?
EBOM-2009 EAp3:Fundamental refrigerant managementposted by Danielle Caestecker on
How do I decide which one to pick?
Exhaust requirement in C&S Building
CS-2009 IEQc5:Indoor chemical and pollutant source controlposted by Rubén M. R. on
We have a C&S building and we asume that it will be occupied by corporate offices.
Change the version of LEED - EB - O & M (V.2008 to v.2009)
EBOM-2009 SSc1:LEED certified design and constructionposted by Paola Figueiredo, Newton Figueiredo on
To whom it may concern, I have a question that I didn not find a solution in the credit-by-credit forum at this website. I have a project LEED-EB-O&M registred in the V.2008 but our client want
Achieve LEED CI Without any Mech. or Plumb. Changes?
CI-2009 EAp1:Fundamental commissioning of building energy systemsposted by Michelle Bracewell-Musson on
I have been asked to bid a LEED CI project where there will only be flooring, wall relocation, and added ceiling tiles to 7,000 feet of a 50,000 foot office space.
Late Enhanced Comissioning
NC-2009 EAc3:Enhanced commissioningposted by Carolina Vergnano on
Does exist any time limit between the construction conclusion and the start of enhanced comissioning? i.e.
All parking underground but one..
CS-2009 SSc7.1:Heat island effect - nonroofposted by Mathilda Jonsson on
Hi! My project has all parking spaces underground exept for one handicap parking that's situated at the court yard. We really want to go for exemplary performance point and put all under cover.
"90% Minimum of building occupants"
NC-2009 IEQc6.1:Controllability of systems - lightingposted by Sandra Heiser on
The requirement reads " Provide individual lighting controls for 90% (minimum) of the building occupants..." Is this based on the FTE? Or does it mean 90% of the individual workspaces?
WE Prerequisite qualification for a minimal CS project
CS-2009 WEp1:Water use reductionposted by Tak Louie on
Our client is building a Retail center for a large grocer with small satellite retail spaces. The balance of the building is simply a parking garage with an enclosed and tempered elevator lobby.
Option 3, approach 2: Random selection
EBOM-2009 SSc4:Alternative commuting transportationposted by gwenedd murray on
This building is over 300,000 sf and located close to public transportation. Half of the tenants are government agencies.