NAF Composites Not CARB

NC-v4 EQc2:Low-emitting materials
posted by  Michelle Rosenberger  on 

There are particleboard products that are NAF with third party certifications that LEED reviewers will not accept because they do not have a CARB exempt executive order.

4
Fri Aug 16, 2019, 6:01 pm

Demand Response Plan - who creates the plan?

NC-v4 EAc4:Demand response
posted by  Deborah Lucking  on 

We have a mechanical engineer, an electrical engineer, a commissioning agent, and an energy modeler.  Looking for advice on who is the appropriate author of such a plan.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4461 thumbs up
Fri Aug 16, 2019, 4:40 pm

exceptions for farmland?

NC-v4 LTc2:Sensitive land protection
posted by  Erica Downs  on 

We have an infill site on a university campus.  Unfortunately, this particular plot of land was previously undeveloped.  When checking the soils survey site, a portion of the site comes u

2
Director of Sustainability
NORR
LEEDuser Expert
7 thumbs up
Thu Aug 15, 2019, 6:02 pm
2
Project Director
WSP USA
LEEDuser Basic Member
381 thumbs up
Thu Aug 15, 2019, 4:40 pm

Permanently installed products definition.

CI-v4 MRc5:Building product disclosure and optimization - material ingredients
posted by  shashank gangil  on 

For MR credits, what exactly contributed as permanently installed product? Does AC ducts and insulation counted here?

2
Architect
CRSA
LEEDuser Basic Member
1 thumbs up
Thu Aug 15, 2019, 3:03 am

Fixtures within Lab Facility - Applicable

NC-v4 WEp2:Indoor water use reduction
posted by  RDK E&S  on 

Hello, 

I'm working on a lab / processing facility aiming for LEED v4 NC certification.

4
Default Avatar
Energy Engineer / Sustainability Specialist
NV5
LEEDuser Basic Member
15 thumbs up
Thu Aug 15, 2019, 1:21 am

SSpc41 Walkable Project Site

NC-v4 INc1:Innovation
posted by  Helene Lefkowitz  on 

Our project team pursued this pilot credit and found it to be very achievable for projects in urban settings.

2
Wed Aug 14, 2019, 9:04 pm

5 Regional Priority Credits

NC-v4 RPc1:Regional priority
posted by  Nathan Gauthier  on 

I was checking the RP credits for LEED v4 NC in Cambridge today and there are only 5 listed (not 6). Boston is the same way.

3
Director of FM Integration and Sustainability
Shawmut Design and Construction
LEEDuser Basic Member
21 thumbs up
Wed Aug 14, 2019, 8:59 pm

LEED 2009 Credit SSc2 Development Density and Community Connectivity

NC-2009 SSc2:Development density and community connectivity
posted by  Andrew Buck  on 

Hello, we are working on a Hotel Project in Chicago, where we had 10 basic services within a 1/2 mile radius, but one of the services (Convenience Market) has closed in the last year (during Constr

3
Default Avatar
Project Architect
KOO LLC
LEEDuser Basic Member
0 thumbs up
Wed Aug 14, 2019, 5:12 pm