social equity within the supply chain
NC-v4 MRc4:Building product disclosure and optimization - material ingredientsposted by Dennis Daniel on
We supply floor covering for LEED v.4 projects. The company I work for has a Code of Conduct that is based on the 10 Principles of the UN Global Compact.
Gross Floor area Question
CI-v4 EQc4:Indoor air quality assessmentposted by Nancy Henderson on
We have a tenant with several full floors being built out in a new core and shell building. Does the gross SF for the purpose of the flush out need to include what would be considered core sp
Membrane Primer VOC – LEED V4 – Healthcare
Healthcare-v4 EQc2:Low emitting materialsposted by Rebecca Barr on
Hi there, we are a fabricator and installer of architectural metal wall panel systems and I was looking for some insight into VOC levels and air and vapour membrane adhesive. We typically use
Select system for the Baseline building according ASHRAE 90.1 -2010 - Proposed wiht Heat pump
NC-v4 EAc2:Optimize energy performanceposted by Konstantina Kalliakoudi on
Hello,
I have following questioning:
My proposed building is nonresidential 710.000 ft2 and the Heating/ Cooling production is made with Chillers and Heat pumps.
Purchased chilled water modelling but pursuing cooling tower use credits
CS-v4 EAc2:Optimize energy performanceposted by Nuttanee Vongveeranonchai on
Dear All,
OPR and BOD documents
NC-2009 EAp1:Fundamental commissioning of building energy systemsposted by Carlos Vazquez on
I accepted an assignment of commissioning a 3,400 sq-ft project to apply for a LEED certification. I came in late in the game.
Chilled Water vs DX System 5 is currently flawed.
NC-v4 EAp2:Minimum energy performanceposted by Alejandro Vera on
At issue, our proposed system (chilled water) is paired against a System 5 (non-residental < 5 floors & 25,000 < SQFT < 150,000) but we are having a problem with the energy modeling wh
Tenants HVAC System Type
CS-2009 EAp2:Minimum energy performanceposted by Amgad Khattab on
We are modeling a Core & Shell office building where the HVAC system is in the tenant scope. we are only delivering chilled water and outdoor air to the tenant areas.
Delete a Campus.
NC-v4 MPR1:Must be in a permanent location on existing landposted by Guillermo Hernandez Espinoza on
I create an example of a campus project registration with the sole objetive of guidance for a client so they can register their project themselves.
Core and Shell Office Building
EBOM-v4 EAp2:Minimum energy performanceposted by Gustav Alfaro on
Hi to all,