Lighting power allowance - loading bays

NC-v4 EAp2:Minimum energy performance
posted by  Ricardo Sá  on 

I am current working on a project looking for certification under LEED V4.

1
Mon Feb 5, 2018, 5:55 pm

Daylighting controls for primary sidelighted areas for baseline

NC-v4 EAp2:Minimum energy performance
posted by  Francesco Passerini  on 

In the refurbishment that was designed internal partitions will be removed and the rooms will become bigger than the existing ones.

1
Mon Feb 5, 2018, 5:50 pm

Recharging Stations - Off-site parking

NC-2009 SSc4.3:Alternative transportation - low-emitting and fuel-efficient vehicles
posted by  Jay Murray  on 

This project is a new 33 story hotel/condo in Boston. There is no parking garage in the building.

3
Jr. Sustainable Building Advisor
Perkins+Will
LEEDuser Basic Member
8 thumbs up
Sat Jan 27, 2018, 12:00 am

Extraction point for Recycled Content

NC-2009 MRc5:Regional materials
posted by  Rick Alfandre  on 

I have steel products that a mfg is providing with certain quantities of post consumer/pre-industrial recycled content.

9
Project Engineer, Construction Services
C.D. Smith Construction, Inc.
LEEDuser Basic Member
0 thumbs up
Fri Jan 26, 2018, 9:55 pm

MRp2 & SSc2

EBOM-v4 MPR2:Must use reasonable LEED boundaries
posted by  Laura Danzig  on 

Hi there.

I have a question regarding identifying the LEED project boundary as it relates to rainwater management.  

2
Editorial Director
BuildingGreen, Inc.
LEEDuser Expert
159 thumbs up
Fri Jan 26, 2018, 8:09 pm

Getting Started

NC-v4 MRc1:Building life-cycle impact reduction
posted by  Mike Workman  on 

Hi All, Our building we are working on is not existing and will be built new on the site. Do we still qualify for Mrc1 option 4?

5
Head of Sustainability
Manens S.p.A.
LEEDuser Basic Member
16 thumbs up
Fri Jan 26, 2018, 5:05 pm