No BAS.
EBOM-2009 IEQc2.3:Occupant comfort - thermal comfort monitoringposted by Melissa Young on
As it says above, achieving this credit without a BAS is difficult. What exactly needs to be done if we don't have a BAS?
Do reused Hospital beds qualify for furniture reuse credit?
CI-2009 MRc3.2:Materials reuse - furniture and furnishingsposted by Bryan Waters on
We would like to pursue this credit, as our hospital floor renovation project registered under LEED CI v 2.0 is reusing all patient beds.
Baseline Fan Power: PFP and AHU Pressure Rises
NC-2009 EAp2:Minimum energy performanceposted by Rodrigo Perez on
We’re working on a 20 stories building that is seeking LEED NC v3 certification. This building considers ASHRAE’s #8 HVAC baseline system: VAV w/ PFP boxes.
Distance between buildling entrance and bicycle storage
CS-2009 SSc4.2:Alternative transportation - bicycle storage and changing roomsposted by William Wong on
I read from Reference Guide that there is distance requirements (200 yards from building entrance) for location selection of bicycle storage for case 1 (commerical or institutional project 300,000
High-rise towers
Pilot-Credits PC23:Quality Viewsposted by Elena Verani on
Would a high-rise tower be compliant with credits requirements? From the upper floors one would only see the sky outside vision glazing. Would this be enough?
Restroom ventilation
NC-2009 IEQp1:Minimum indoor air quality performanceposted by Alexia Anastassiadis on
We are working on a major renovation project and the restrooms have natural ventilation. Do we have to provide additional mechanical exhaust to comply with ASHRAE?
CS projects should have 75% of GFA to earn this credit?
EBOM-2009 SSc1:LEED certified design and constructionposted by Bazeeth Ahamed Khader Mohamed Ali on
75% of "leasable area" makes more sense here. How do we communicate our suggestions to USGBC. Kindly let me know if there is a way.
Industrial Plant Manufacturing Hall Ventilation
NC-2009 IEQp1:Minimum indoor air quality performanceposted by Sustainability Provider on
We are currently working on the design of an industrial plant (aluminum casting in specifics) with two sections - manufacturing hall and administrative/engineering offices.
Energy Star Space Allocation
EBOM-2009 EAp2:Minimum energy efficiency performanceposted by Ed Okon on
Good Afternoon I'm currently composing a plan for LEED EB on an existing manufacturing campus comprised of multiple building types (warehouse, shipping and receiving facility, manufacturing, office
Sample Calculations
NC-2009 WEc2:Innovative wastewater technologiesposted by Craig Phillips on
I am finding it hard to locate a 1.0 or a dual flush 1.6/.8 toilet and flushometer. Where did the data come from in the sample calculations? Lyn