Credit 3.2, Option 1, Path 2
NC-2009 IEQc3.2:Construction IAQ management plan - before occupancyposted by Douglas Blakeslee on
We are the GC for a new small (4,000 SF) Leed Certified fast food restaurant with 3,800 CFM of outside air when occupied. We plan to do our initial 3,500 CF/SF flushout over a weekend.
Phased IAQ Testing?
Schools-2009 IEQc3.2:Construction IAQ management plan - before occupancyposted by Q + on
Is it acceptable to perform air quality testing in phases? The project in question is a 175K sf school designed in 7 zones.
IAQ Testing and Furnishings
Schools-2009 IEQc3.2:Construction IAQ management plan - before occupancyposted by Q + on
The Credit Language contains this statement regarding air quality testing and furnishings: "Movable furnishings such as workstations and partitions should be in place for the testing, although it
Supervising the Commissioning of 20% of the energy systems
NC-2009 EAc3:Enhanced commissioningposted by Maya Karkour on
Hello, We are working on a project in which all the energy systems will be installed, tested and balanced by the general contractor.
Emission Reporting using Energy Star
EBOM-2009 EAc6:Emissions reduction reportingposted by Simon Sue on
When i click on the "select view" then to Performance :GHG emission, i can see the current total GHG emission value, but when i try to generate SEP (Statement of Energy Performance) report, the GH
EAp2 Equipment Motors
CI-2009 EAp2:Minimum energy performanceposted by Eric Claycamp on
For a LEED CI project that includes a fitness center, do you count the motors in the treadmills and cross trainers? No fitness equipment I have found is Energy Star rated.
Using as ID credit in New Construction, indoor & outdoor
EBOM-2009 MRc4:Sustainable purchasing - reduced mercury in lampsposted by Sarah Corbitt on
I'm working on a project which is using this credit as an ID credit for LEED-NC. Must outdoor lights be included?
EAc1 required 2 points
CI-2009 EAp2:Minimum energy performanceposted by Jennifer Berthelot-Jelovic on
I know that for EAc1 there was a requirement that "All LEED for New Construction project registered after June 26, 2007 are required to achieve at least two (2) points." Since I am working on a LEE
LEEDuser plumbing assessment template updated
EBOM-2009 WEp1:Minimum indoor plumbing fixture and fitting efficiencyposted by Tristan Roberts on
To all LEEDuser members using our Water Efficiency Economic Assessment Policy for WEp1: we have made a couple minor updates to it to improve it relative
Flow Regulators with Pressure Compensation
EBOM-2009 WEp1:Minimum indoor plumbing fixture and fitting efficiencyposted by Surenthira Stephen Ramachanderan on
Hi Dan, I m currently doing couple of LEED C&S buildings.