producer declaration
CS-2009 MRc4:Recycled contentposted by Agnieszka Rylska on
We received a declaration from a material producer stating that the product "contains ca. 80% recycled content" and "we assume that 50% comes from post-consumer".
Minimum Energy performance Calculator
NC-2009 EAp2:Minimum energy performanceposted by Vassil Vassilev on
Greetings, We have a project, which is registered upon LEED-NC v2009, with unit type SI. The online form of EAp2 has a new form, which is directing us to upload the Minimum Energy Performance Calcu
Locker rooms
CI-2009 IEQc1:Outdoor air delivery monitoringposted by Agnieszka Rylska on
Are CO2 sensors required in locker rooms? Loker rooms are non-regularly occupied spaces but they are also densely-occupied spaces.
Petrol contamination
NC-2009 SSc3:Brownfield redevelopmentposted by Alicja Bieszyńska on
My project site is located next to one of the main arteries of Warsaw. Due to the high trafic the strip adjacent to the road is contaminated with petrol related substances (not much but still).
pressure drop adjustemnt in the baseline model
CS-2009 EAp2:Minimum energy performanceposted by Agnieszka Rylska on
I have two questiones: 1.
parking demand vs 1000sf or vs employees
posted by Agnieszka Rylska on
We are working on a project that is a warehouse.
Commissioning of DATA Centers
Data-Centers-NC-v4 EAc1:Enhanced commissioningposted by Vassil Vassilev on
Greetings, There is a question from the Owner of Data center in respect of the forth comming commissioning process for his project. The question is related to the specific IT equipment and the spec
IEQp1-tenant spaces
CS-2009 IEQp1:Minimum indoor air quality performanceposted by Agnieszka Rylska on
We are working on a shopping mall project in whcih there will be many retail spaces. Some of the tenants will design their own ventilation systems and provide their own AHUs.
Use of C&S Commissioning documentation
EBOM-2009 EAc2.1:Existing building commissioning - investigation and analysisposted by Izabela Kwiecinska on
Hi Everyone, We are working on a building that already got LEED C&S certificate in 2012 and now aims to get EBOM.
Heating only system; Baseline modeling of DHW
NC-2009 EAp2:Minimum energy performanceposted by Vassil Vassilev on
Markus, thanks a lot for your answer. Another issue appeared to this Heating only system - Baseline modeling of DHW (Domestic Hot Water). The Proposed model is having a gas fired boiler to provide