Habitable buildings

ND-Plan-v4 MPR3:Must comply with project size requirements
posted by  Antonio Macedo Filho  on 

Hi, Eliot! 
The project must have at least two habitable buildings, but it would necessarily residential buildings? Would this "habitatable" word be in the sense of residence itself?

2
LEED AP-ND, Principal
Criterion Planners
LEEDuser Expert
231 thumbs up
Wed Oct 11, 2017, 2:23 pm

Strategy A - 2500 cd/m2

NC-v4 EQc6:Interior lighting
posted by  Filipe Boni  on 

I`m trying to understand the Option 2 -Strategy A and having difficulty of finding this illuminance on brazilian cutsheets. Is this information that I need to look at?

2
Tue Sep 19, 2017, 6:59 pm

Exempt area of 10% in a Group Project

LEED Guidance for Campuses and Multiple Buildings
posted by  Gabriel Frasson  on 

We have a site that contains two buildings that are being certificate as a campus project. In the ground floor of Tower A there are some stores that we want to exempt of the certification project (

1
Thu Jan 21, 2016, 1:03 pm
1
Sun Aug 27, 2017, 12:07 am

VRP Compliance Calculator or 62MZCalc for projects outside U.S.?

NC-2009 IEQp1:Minimum indoor air quality performance
posted by  Geraldo Pithon  on 

I am submitting for review a project outside the US, in Brazil. The legislation of Brazil is very similar to that specified by ASHRAE 62.1.

1
Thu Feb 11, 2016, 10:33 pm

Calculation

NC-v4 EAc7:Green power and carbon offsets
posted by  Vitor Tosetto   on 

Dear All, I have a doubt about calculation of quantity of REC. I believe you can help me. Using the Example 1 (in page 460 of v4) my project will consume 1,98 MWh per year.

1
Wed Nov 30, 2016, 3:01 pm

Zone Calculation Ds% for VAV System

NC-2009 IEQp1:Minimum indoor air quality performance
posted by  Marina Andrade  on 

I received this question in IEQp1: "The ventilation calculations indicate that the value of the flow rate of air projected under the condition tested (DS) was modeled as 100% level for each of th

1
Mon Nov 17, 2014, 3:08 pm

Alarm to closed openings

NC-v4 EQp1:Minimum indoor air quality performance
posted by  Vitor Tosetto   on 

Dears, When we have a Naturally Ventilated Space, we can use an alarm to indicate that the openings are close. Someone know if I can use an light alarm? or I must use an sound alarm?

0

VRF system

NC-2009 EAp3:Fundamental refrigerant management
posted by  GISELA FARHAT DE ARAUJO  on 

We are using the vrf system on a project. Should i put as type of equipment Split AC or should i chose the "others" option?

1
Mon Jun 27, 2016, 6:00 pm

Dist. Center - Light polution

Warehouses-NC-v4 SSc6:Light pollution reduction
posted by  Antonio Macedo Filho  on 

If the design of a distribution center worked 24 hours in 3 shifts, even at night, could we not get that credit? If we use external lighting with zone presence sensors would not it be possible?

1
Mon Aug 28, 2017, 3:55 pm