Forum quick links
Core and Shell v3 w/ ASHRAE 90.1-2010 w/o tenant agreement
CS-2009 EAp2:Minimum energy performanceposted by Curtis Clark on
We are working on a very large, core and shell project that the owner will not share the tenant agreement with our team. The minimum code requirements are based on IECC 2012/ASHRAE 90.1-2010.
Pre-Consumer Recycled Content
EBOM-v4 MRc1:Purchasing - ongoingposted by Claire Bannister on
How is pre-consumer recycled content calculated in v4? In v2009, there were columns for both pre- and post- consumer.
PIf2
NC-2009 PIf2:Project Summary Detailsposted by shaun Andriano on
This might be an easy one... Our PI form 2 was recently not approved following final design review.
Different work week lengths
EBOM-v4 LTc1:Alternative transportationposted by Claire Bannister on
Our facility has office staff who work Monday-Friday, and production staff who work Monday-Thursday...
California Projects using Title 24-2013
NC-2009 EAp2:Minimum energy performanceposted by Cindy Quinn on
To comply with California codes we had to show compliance with Title 24-2013. This required us to use the proprietary program Energy Pro 6.
Calculating Daily Average for Transient Users
NC-2009 PIf3:Occupant and Usage Dataposted by Randy Weatherly on
Based on the examples presented on this site, the daily average is based on 365 days a year. Is this correct or should it be based on actual days the facility is open for business? Thanks
Roof/Terrace
NC-2009 SSc7.2:Heat island effect - roofposted by Lauren Bellamy on
The project I am working on has a canopy over a terrace, and below the terrace is conditioned space.
77 Olfactory Comfort
posted by Carina Clark on
If a commercial project is looking to provide a kitchen/break room, some options include a separation by negative pressurization and hallways.
LEED Online Not Displaying Multiple Credit Assignees
posted by Peter Warren on
If I am NOT the a project’s LEED Administrator, how can I see the full list of team members to whom a credit is assigned (i.e. when it is assigned multiple people)?
WEc1 - We don't really have a "SITE" outside of the building env
Retail-NC-v2009 WEc1:Water efficient landscapingposted by Lou Niles II on
Hello I am working on Two Separate projects that actually overlap on a site; they are not registered as Master Site or Campus and we don't want that at this time. Project A Surrounds Projects B. Pr