NC-2009 IEQc4.1:Low-emitting materials - adhesives and sealantsposted by Donna Juselis on
deleted
Heat Island Reduction when adjacent to existing building on lot
CS-v4 SSc5:Heat island reductionposted by Nadia Bini on
Hello, our project is connected to an existing building on the same lot. Can we exclude the existing building's roof surface from our credit calculations?
Plant Design for Proposed bldg
NC-2009 EAp2:Minimum energy performanceposted by Julian Park on
If a new building will be served by an existing chiller plant that already serves an existing building, does the Plant design for the Proposed Alternative need to model the full chiller size, even
Paint Certification
NC-v4 EQc2:Low-emitting materialsposted by Rai Galang on
Just want to check if Green guard certification for the paint is approved for the LEED when applying for the Credit instead of Green Seal (GS-11) certification?
Ceiling Step Down
NC-v4 EQc8:Quality viewsposted by Kim Lombard on
Does anyone have a good sense of how to treat step down ceiling heights in calculating the interior distance qualifying for quality views?
Upload IEQc3.2-1. Provide the IAQ Management Plan...
NC-2009 IEQc3.2:Construction IAQ management plan - before occupancyposted by Zach Hoffman on
Hello, I have been successfully completing IAQ Testing under Option 2 for a few years now and always wondered about this section of the credit template.
LEED O+M: Multifamily
NC-v4 MPR3:Must comply with project size requirementsposted by Adam Stoker on
Where can I go to find information on the project size requirements for LEED O+M: Multifamily projects?
Campus Site Lignting Calcs - again, sorry
CS-2009 EAp2:Minimum energy performanceposted by charles bell on
We submitted (on Jan 23, 2014) the question below. Unfortunately, since then my email has crashed and I have lost the response. Is there any way this can be recovered?
CHP Plant Electricity Generation Credit and Efficiency Calcs
NC-2009 EAc1:Optimize energy performanceposted by MKK LEED on
We are working on a higher ed. project building connected to a campus-wide district heating/cooling and power plant.
How to apply base ratios for non-specified usage type?
CI-v4 LTc5:Reduced parking footprintposted by Jonathan Weiss on
For a laboratory / office building, how do you apply the baseline? It appears that you pro-rate the usage by area of each space type, but laboratories are not a listed usage type.