500 miles or 100 miles?

EBOM-2009 MRc1:Sustainable purchasing - ongoing consumables
posted by  Becky Stumm  on 

In the credit language above, and corresponding LEED User calculator resource states manufacturing and distribution should be within 500 miles of the project, but my LEED EBOM v4 book from LEED say

1
Mon Jan 30, 2017, 4:59 pm

Rooftop smoking areas?

CS-2009 IEQp2:Environmental Tobacco Smoke (ETS) control
posted by  Sara Neff  on 

How is the 25' radius applied when the smoking area is on a rooftop? Do we assume the smoke drifts up or do I need to worry about windows below the smoking area?

1
Sat Aug 26, 2017, 10:59 pm

R-Value for wall assembly

NC-2009 EAp2:Minimum energy performance
posted by  Sunil S  on 

I am working on a residential building, the exterior wall assembly as R-19 fill cavity between studs for an 3.5" depth (wood studs 2x4 16" OC) but in the ASHRAE table A3.4, there is no value menti

1
Thu Aug 17, 2017, 3:45 pm

Site adjacent to 5 lane highway - with no On-0ff ramp.

Warehouses-NC-v4 LTc4:Surrounding density and diverse uses
posted by  Joyce Kelly  on 

If the Distribution center is less than 1-mile driving distance of 5 lane, wide shouldered Carlyle turnpike aka Route 11 (center lane = turning lane), does that qualify as a highway for the purpo

1
Tue Jan 17, 2017, 9:25 pm

v09 Water Use Reduction Additional Guidance available

NC-2009 WEp1:Water use reduction
posted by  RETIRED   on 

As part of the October 2016 LEED addenda update (http://www.usgbc.org/articles/leed-addenda-update-october-2016), USGBC updated the Water User Reduction Guidance document to Version 9 (http://www.u

0

data center equipment not listed in DOE Energy Star categories

CI-2009 EAc1.4:Optimize energy performance - equipment and appliances
posted by  Gail Napell  on 

Servers are listed on the Energy Star website, but not receivers. Is it safe to assume they are still not Energy Star eligible?

1
Mon Oct 12, 2015, 6:56 pm

Contacting the USGBC and Combining Tenant Spaces

CI-2009 PIf1:Minimum Program Requirements
posted by  CHRISTIAN LUTJEN  on 

Hello, we have been trying to get an answer from the USGBC for two days short of a full month now.

1
Thu Nov 12, 2015, 4:40 pm

Total Site Area within LEED Project Boundary

NC-2009 PIf2:Project Summary Details
posted by  Sara Goenner Curlee  on 

I feel like I should know this, but can someone confirm for me whether or not the building footprint is included in the Total Site Area?

1
Fri Feb 10, 2017, 9:38 pm

recessed walk off mat

EBOM-2009 IEQc3.5:Green cleaning - indoor chemical and pollutant source control
posted by  Bomin Kim  on 

We are specifying a recessed walk off mat for the building in the vestibule (8' long). I remember that if the walk off mat is 10', a point is granted.

1
Thu Apr 14, 2016, 11:29 pm

Fabricator's location

NC-2009 MRc5:Regional materials
posted by  Mahsa Nicknam  on 

IF the manufacturer's location is within 500 miles however fabricator's location is not, does it still have contribution to this credit OR not? In another word, when manufacturer location is withi

1
Sun Mar 15, 2015, 5:57 pm