CS v2009 ventilation need for each space
CS-2009 IEQp1:Minimum indoor air quality performanceposted by MERVE AYGENC on
Does each space need to achieve the airflow suggested by ASHRAE separately or do we considered the overall achievement while using Minimum IEQ Performance Calculator?
Museum Building / Gallery Areas
NC-v4 EQc9:Acoustic performanceposted by O Moltay on
Hi, we have a museum project with general exhibition areas: are there specific values for "Reverberation time requirements", as there are not similar room type in the table 2 of reference guide?
opaque building envelope construction
NC-v4 EAp2:Minimum energy performanceposted by Ahmed El-Semary on
i need to know what is required to be filled exactly in roof construction and whatis meant by building ID ??
Survey Participants
EBOM-2009 IEQc2.1:Occupant comfort - occupant surveyposted by Fareed Alghimlas on
We’re working towards the certification of a large office building, where a good portion of the (FTEs) are subcontractors who spend time (minimum 40hrs/week) in the building but don’t necessarily h
Number of transients for FTE calculation
posted by Sunanda Swain, LEED AP BD+C, PQP on
Hi, I am working on a LEED for Healthcare project (LEED HC v2009). At the moment I am filling out the scorecards. I am bit confused about calculating number of pick hour transients.
Greenfield or previously developed?
NC-2009 SSc5.1:Site development - protect or restore habitatposted by Ilan Yahav on
I'm wondering if a project I'm working on, situated near the coast in Israel, is considers a greenfield or developed area.
Stormwater Management Plan
NC-2009 SSc6.2:Stormwater design - quality controlposted by Nisreen Alhussein on
I cant find clear cut for Stormwater Management Plan definition, i mean is it using both structural and non structural plans to achieve stormwater quality control?
Chilled water flow and pipe sizes
CI-2009 EAc1.3:Optimize energy performance - HVACposted by Jayakumar Pamuri on
Hi All, I am here to post my query about chilled water system,flow and pipe sizes.
Proposed case cooling capacity reducing energy savings
NC-2009 EAc1:Optimize energy performanceposted by SSN Energy Model on
Hi, I am doing energy simulation for G+4 Labor Accommodation building. In base case, i have considered 2.66 COP.