Forum quick links
Tile finishes for flat roof
CS-2009 SSc7.2:Heat island effect - roofposted by Magda Aghababyan on
We are working project C&S the client need to use white colour ceramic tile on roof top.Should need to test it ? and value has to be more than 78 for the flat roof ?
Blind
CI-v4 EQc5:Thermal comfortposted by Ameet AA on
Hi, Can blind be considered as control for thermal comfort? Thanks.
Certify some of multiple fitout floor
CI-2009 MPR2:Must be a complete, permanent building or spaceposted by sompoche sirichote on
Our client will rent 8,10-20 floor within 20 stories building. They would like to get LEED CI certify only for 8 and 10 floor. Can it be done under single project certification?
Glass Doors
NC-2009 IEQc8.1:Daylight and views - daylightposted by John Covello on
Hello, Do Glass Doors count as windows and require automatic glare control?
Alternative Outdoor Air Supply for Basement Parking
CS-2009 IEQp1:Minimum indoor air quality performanceposted by Katherine Ann Resurreccion on
Hi All, We would like to get your opinion in the situation below if approach is acceptable to IEQp1: We have an enclosed Driver’s lounge, Lift lobbies and Administration office at the Basement fl
Recycled content in Steel frame of facade
NC-2009 MRc4:Recycled contentposted by Indochine Engineering VN on
Hi, I would like to ask in case that facade manufacturer cannot confirm recycled content in their steel frame of facade, can I use default number 25% recycled content for steel product as stated in
Building facade facing circulation network not more than 1ft
ND-v4 NPDc1:Walkable streetsposted by Kristina Pobre on
I'm a bit confused with why LEED ND is putting a point on this specific criteria.
Fresh air supply using Cooling pad in Production area
NC-2009 IEQp1:Minimum indoor air quality performanceposted by SAMY Chamy on
Dear all Our project is single storied sewing factory in production area we have large size Exhaust fans in one side and opposite side of exhaust fan have cooling pad Now the issue is we can't p
Project space Owned & Leased partly
CI-2009 MRc1.1:Tenant space - long-term commitmentposted by Nandana Kumar on
Hi I have a project where out of the total project area, the owner owns 75% of the project spaces and remaining 25% is leased (lease period 3 years).
Energy modeling
CI-2009 EAc1.3:Optimize energy performance - HVACposted by Muzammal Abbas on
Dear Sir, I want to know that is it mandatory to provide energy modeling for commercial interior project's for LEED submission, Now my second question is that i am using a HAP 4.8 and eQUEST softwa