Accidentally Opened Awarded Credit during Appeal Stage
posted by Bernard Sagaiyaraj on
My team member accidentally opened 2 awarded credits during the Appeal Stage for some other non-compliance credits. No changes were made to the form.
Option-3: Irrigation Meter Installed
EBOM-v4 WEc1:Outdoor water use reductionposted by VISHESH AGARWAL on
i am working on the project where project team use the STP Non potable water used for irrigation purpose. so i am reducing the 100% potable water. can i sufficient to achieve this credit.
Project located in a building with a very low fresh air rate
Retail-NC-v4 EQp1:Minimum indoor air quality performanceposted by Valentin Grimaud on
What if the project is located inside a 30-year old building with AHU supplying less than 10% fresh air rate? As we have to use the centralized ventilation system and we couldn't make any change t
WE Credit 4.2: Cooling Tower Water Management- non potable
EBOM-2009 WEc4:Cooling tower water managementposted by satheesh M on
The project’s cooling requirement is being met by both chiller plant inside the project boundary as well as the chiller plant in the Building Owned DES.
Amenities Within Main Building
posted by Aswin M on
We have a Retail Commercial Interior project inside a Main building.
Modeling OA with Demand control ventilation
CS-2009 EAp2:Minimum energy performanceposted by Indochine Engineering VN on
Hi, I have demand control ventilation for every AHU.
Is it too late to do SSp1?
NC-2009 SSp1:Construction activity pollution preventionposted by Indochine Engineering VN on
Hi, My project is a hotel and client just decided to do LEED when Construction of structure is almost done.
Proposed Case-Process Load
NC-v4 EAp2:Minimum energy performanceposted by Muzammal Abbas LEED AP (BD+C) on
Hi, Is there any limitations in LEED V4 regarding process energy that it should be minimum 25% (In proposed case) of the baseline energy cost for the building.
Dormitory as support building
NC-2009 PIf2:Project Summary Detailsposted by ABDUL MUTHALIB MOHAMED on
We would like to register a factory building in Bangladesh. Th built up area of factory building is 2 lakh SFT, Ground level only.