Recycled content in Steel frame of facade

NC-2009 MRc4:Recycled content
posted by  Indochine Engineering VN  on 

Hi, I would like to ask in case that facade manufacturer cannot confirm recycled content in their steel frame of facade, can I use default number 25% recycled content for steel product as stated in

1
Mon Jan 11, 2016, 6:18 pm

Building facade facing circulation network not more than 1ft

ND-v4 NPDc1:Walkable streets
posted by  Kristina Pobre  on 

I'm a bit confused with why LEED ND is putting a point on this specific criteria.

0

Fresh air supply using Cooling pad in Production area

NC-2009 IEQp1:Minimum indoor air quality performance
posted by  SAMY Chamy  on 

Dear all Our project is single storied sewing factory in production area we have large size Exhaust fans in one side and opposite side of exhaust fan have cooling pad Now the issue is we can't p

1
Mon Mar 14, 2016, 1:11 pm

Project space Owned & Leased partly

CI-2009 MRc1.1:Tenant space - long-term commitment
posted by  Nandana Kumar  on 

Hi I have a project where out of the total project area, the owner owns 75% of the project spaces and remaining 25% is leased (lease period 3 years).

1
Sat Aug 26, 2017, 10:36 pm

Energy modeling

CI-2009 EAc1.3:Optimize energy performance - HVAC
posted by  Muzammal Abbas  on 

Dear Sir, I want to know that is it mandatory to provide energy modeling for commercial interior project's for LEED submission, Now my second question is that i am using a HAP 4.8 and eQUEST softwa

1
Mon Dec 1, 2014, 3:07 pm

LEED NC V2009 - Data Center

NC-2009 EAp2:Minimum energy performance
posted by  SW LEE  on 

Our project owner would like to register a Data Center under LEED NC V2009. May I know, do anyone know how to simulate the data center?

1
Mon Apr 25, 2016, 3:46 pm

Number of CO2 Sensors

CI-v4 EQc1:Enhanced indoor air quality strategies
posted by  Subramaniam Chandrasekaran  on 

regarding the number of CO2 sensors, I have the following query; requesting for advice; do we have to install - 1. one CO2 sensor for every 1000 sqft 2.

1
Sat Aug 26, 2017, 6:39 pm

office building

Retail-NC-v4 WEc4:Water metering
posted by  Zahid Ahmed  on 

recently appointed as FM in commercial office building. what to do if we want to go for LEED certification. need details. thank you

2
Founder & Community Director
Metricorps
LEEDuser Expert
7783 thumbs up
Thu Aug 17, 2017, 11:17 am

Energy modeling for LEED BD+C: Core & Shell

NC-v4 EAp2:Minimum energy performance
posted by  Hanh Truong  on 

Dear all, We have a project targeting LEED BD+C: Core & Shell. My question is how to model whole-building energy simulation?

2
Tue Aug 1, 2017, 3:00 pm

Exterior lighting design

CI-2009 EAc1.3:Optimize energy performance - HVAC
posted by  Sivarajah Ragulakeethan  on 

Hi, We are working on commercial interior projects. While doing the model we didn't receive exterior lighting design.

4
Tue Aug 1, 2017, 3:00 pm