WE Prerequisite 1
EBOM-v4 WEp1:Indoor water use reductionposted by Alice Andersen on
I have a lavatory faucet that are automatically controlled (sensor control) and a flow rate of 5 l per minute. In accordance to the LEED manual the baseline is 1.9 l per minte.
Option 2 - Leadership Extraction Practices
CS-v4 MRc3:Building product disclosure and optimization - sourcing of raw materialsposted by Sara Johansson on
How can structure and shell only be allowed to contribute towards 30% of the compliant building material cost, when 25% is enough to fullfil this credit?
LEED Basement Boundary
Healthcare-v2009 MPR3:Must use a reasonable site boundaryposted by Patrice McVeigh on
Hi, I am working on a project with 3 towers over a shared 2-storey basement. Each tower is being certified separately.
Under building Parking roof area calculations
CS-v4 SSc5:Heat island reductionposted by Timo Rintala on
We have had recent guide from USGBC, that also in case of under building parking roof SRI requirements are to be met. Even if there is eight floors of office in between.
Open fireplaces
NC-v4 EQp1:Minimum indoor air quality performanceposted by Cristina Florit on
I am working in a hotel project where open fireplaces are being considered.
Testing Procedure
Pilot-Credits EQpc57:Enhanced acoustical performance - exterior noise controlposted by Margaret Hamilton on
We're pursuing this pilot credit for a project in the UK.
Tenant Guidelines credit substitution to v4?
CS-2009 SSc9:Tenant design and construction guidelinesposted by Maria Porter on
Now that Tenant Guidelines in v2009 are a bit dated, I’m referring to that CI v2009 no longer exists for new projects, wouldn’t it make more sense to use v4 credit requirements instead?
Rc value
NC-v4 EAc6:Enhanced refrigerant managementposted by Lise Dannesboe on
Hi
To caluclate the Rc-value we need to know the amount of refrigerant and the cooliing capacity. As LEED v4 puts it: