Forum quick links
Existing building, physically sepatated from new construction
NC-2009 PIf2:Project Summary Detailsposted by Michela Tedeschi on
We are working on a new constuction in Italy under LEED Certification (NC 2009). An existing building, physically sepatated from the new construction, is located inside the LEED Boundary.
Option 1: Equipment Efficiency
CI-2009 EAc1.3:Optimize energy performance - HVACposted by Ricardo Sá on
Hi, I have several compact rooftop units serving a big sales area. However, only 80% of them is actually new equipment that meet the credit's criteria.
storage of rain water
NC-v4 WEp1:Outdoor water use reductionposted by Francesco Passerini on
Does the storage of rain water contribute to achieve this prerequisite? The project will irrigate the outdoor vegetation only with rain water.
Heat recovery and dehumidification
NC-2009 EAp2:Minimum energy performanceposted by Francesco Passerini on
In a swimming pool removing latent heat is necessary all the year round. For the baseline model, if I model the heat recovery according to G3.1.2.10 Exhaust Air Energy Recovery (50% both sensible a
Standing human activity
NC-2009 IEQc8.2:Daylight and views - viewsposted by VICTOR MORENO on
Hello, I am working in a Museum project.
n/a
NC-2009 EAp2:Minimum energy performanceposted by Francesco Passerini on
G3.1.2.5 states: Ventilation.
Core & Shell without HVAC or electrical systems
CS-2009 MPR2:Must be a complete, permanent building or spaceposted by Celia Puertas Romero on
We would like to pursue LEED Core & Shell certification for a building undergoing a major renovation.
Continuous Monitoring Sensors
EBOM-v4 EQc3:Thermal comfortposted by Laura Danzig on
Hi there, a quick question regarding the locations of the sensors/measurements required for this credit.
Error in eQUEST in the Perform Compliance Analysis
CS-2009 EAp2:Minimum energy performanceposted by Toni Herena Montull on
Dear all, I am stuck with an error from eQUEST.
Integrative Process-Simple box C&S v4
CS-v4 IPc1:Integrative processposted by Giuseppina Amorusi on
Hi all, I and my team are working on LEED v4 BD+C project, and we're looking to pursue the Integrative Process credit for Core and Shell certification. We have an existing building where we will do